Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
02/07/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2685-228 T22-M0012

Permit Reviews

Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Start Date Submittal Complete Date Status  
02/08/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 02/15/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Total Outstanding Activity Conditions - 6
Date Name
02/08/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/08/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/08/2024 Post-Installed Anchor Inspection Report is required.
02/15/2024 Post-Tension Inspection Report is required.
02/15/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
11/22/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Date Description Comments
03/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
11/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00802
Permite Description: SFR BT2685-228 T22-M0012
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
03/28/2024 COT - RSEL - Grounding/Bonding N/A Not Applicable
08/14/2024 RSBU - Building Progress N/A Partial Pass Construction is 75% complete. Main water line is not connected to city water, electrical meter is not installed by TEP, driveway, sidewalk, and front entry concrete is not poured, backyard fencing is not installed, and landscaping is not completed.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00802
Permit Description: SFR BT2685-228 T22-M0012
Total Completed Inspections - 20
Date Description Inspector Results Comments
03/13/2024 COT - RSPL - Yard Water Line Passed Meter not installed, line is under air pressure test and holding 60 pounds of compressed air. Okay to shade pipe and backfill trench.
03/13/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to main sewer line and under a water test with no leaks. Okay to shade pipe and backfill trenches.
03/28/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
03/28/2024 COT - RSEL - Electrical Underground Passed
03/28/2024 COT - RSBU - Preslab Passed
04/18/2024 COT - RSBU - Exterior Clips/Sheathing Passed
04/19/2024 COT - RSBU - Roof Nailing Passed Roof trusses are installed per truss calcs with the correct number of rat runs and H2.5 clips installed on each rafter and floor joists. Okay to proceed with dry-in of roof.
05/31/2024 COT - RSPL - Gas Pressure Test Passed
06/04/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/14/2024 BULD - Electrical Clearance Passed TEP ECO
06/28/2024 COT - RSBU - Interior Shear Bracing Passed 6/28/24: 3rd bedroom sheet rock is properly screwed off per plan for an interior shear wall.
08/13/2024 COT - BULD - SWG Clearance Passed
08/19/2024 COT - RSPL - Sewer Passed
09/17/2024 RSBU - Building Progress Passed
09/17/2024 COT - RSEL - Electrical Final Passed
09/17/2024 COT - RSEL - Outdoor Lighting Passed
09/17/2024 ENGR Engineering Final Passed
09/18/2024 COT - RSME - Mechanical Final Passed
09/18/2024 COT - RSPL - Plumbing Final Passed
09/18/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 3 - LOT 17 START_V1.PDF DOCUMENTS VIEW
BT III 17 SIC-2024-02-07_V1.PDF DOCUMENTS VIEW