Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0323-00802
Permit Details
Apply Date:
02/07/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2685-228 T22-M0012
Permit Reviews
Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/08/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/15/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
02/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
02/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
02/08/2024 | Post-Installed Anchor Inspection Report is required. |
02/15/2024 | Post-Tension Inspection Report is required. |
02/15/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
11/22/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0323-00802
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Date | Description | Comments |
---|---|---|
03/22/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
11/22/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00802
Permite Description: SFR BT2685-228 T22-M0012
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/28/2024 | COT - RSEL - Grounding/Bonding | N/A | Not Applicable | |
08/14/2024 | RSBU - Building Progress | N/A | Partial Pass | Construction is 75% complete. Main water line is not connected to city water, electrical meter is not installed by TEP, driveway, sidewalk, and front entry concrete is not poured, backyard fencing is not installed, and landscaping is not completed. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00802
Permit Description: SFR BT2685-228 T22-M0012
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/13/2024 | COT - RSPL - Yard Water Line | Passed | Meter not installed, line is under air pressure test and holding 60 pounds of compressed air. Okay to shade pipe and backfill trench. | |
03/13/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing is connected to main sewer line and under a water test with no leaks. Okay to shade pipe and backfill trenches. | |
03/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
03/28/2024 | COT - RSEL - Electrical Underground | Passed | ||
03/28/2024 | COT - RSBU - Preslab | Passed | ||
04/18/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
04/19/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are installed per truss calcs with the correct number of rat runs and H2.5 clips installed on each rafter and floor joists. Okay to proceed with dry-in of roof. | |
05/31/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
06/04/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
06/14/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
06/28/2024 | COT - RSBU - Interior Shear Bracing | Passed | 6/28/24: 3rd bedroom sheet rock is properly screwed off per plan for an interior shear wall. | |
08/13/2024 | COT - BULD - SWG Clearance | Passed | ||
08/19/2024 | COT - RSPL - Sewer | Passed | ||
09/17/2024 | RSBU - Building Progress | Passed | ||
09/17/2024 | COT - RSEL - Electrical Final | Passed | ||
09/17/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
09/17/2024 | ENGR Engineering Final | Passed | ||
09/18/2024 | COT - RSME - Mechanical Final | Passed | ||
09/18/2024 | COT - RSPL - Plumbing Final | Passed | ||
09/18/2024 | RSBU - Building Final | Passed |