Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
08/21/2023
Applicant:
Brianna Quiroz
Description:
Roosevelt Model SFR La Estancia

Permit Reviews

Permit Number - TC-MDP-0323-00740
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia
Start Date Submittal Complete Date Status  
08/23/2023 RESTAMP - RESIDENTIAL v.1 08/23/2023 APPROVED Review Details
08/22/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 08/23/2023 APPROVED Review Details
10/03/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 10/04/2023 APPROVED Review Details
07/16/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/17/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0323-00740
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia
Date Description Comments
08/23/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
07/16/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/22/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/16/2023 Post-Tension Inspection Report is required.
07/16/2024 Post-Tension Inspection Report is required.
08/07/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/16/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
08/07/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/16/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
02/16/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
07/16/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0323-00740
Permite Description: Roosevelt Model SFR La Estancia
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/27/2023 COT - BULD - SWG Clearance N/A Not Applicable
10/27/2023 COT - RSPL - Gas Pressure Test N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0323-00740
Permit Description: Roosevelt Model SFR La Estancia
Total Completed Inspections - 19
Date Description Inspector Results Comments
10/27/2023 COT - RSPL - Rough Soil Passed
11/08/2023 COT - RSEL - Grounding/Bonding Passed
11/08/2023 COT - RSBU - Preslab Passed
11/08/2023 COT - RSEL - Electrical Underground Passed
11/08/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
12/18/2023 COT - RSBU - Roof Nailing Passed Roof sheathing is properly installed and nailed off. Okay to proceed with roofing dry-in.
12/18/2023 COT - RSBU - Exterior Clips/Sheathing Passed All H2.5 clips are properly installed on roof rafters. All hold downs are properly nailed to wall studs. All straps are properly nailed off. Plywood sheathing for exterior and interior shear walls are properly nailed per plan. Okay to proceed with exterior stucco prep.
02/21/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
02/29/2024 COT - RSBU - Interior Shear Bracing Passed
03/04/2024 COT - RSPL - Sewer Passed
03/15/2024 BULD - Electrical Clearance Passed
05/16/2024 ENGR Engineering Final Passed
07/11/2024 COT - RSPL - Yard Water Line Passed
07/16/2024 COT - RSEL - Outdoor Lighting Passed
07/16/2024 COT - RSME - Mechanical Final Passed
07/16/2024 COT - RSPL - Plumbing Final Passed
07/23/2024 RSBU - Building Progress Passed
07/24/2024 COT - RSEL - Electrical Final Passed
07/24/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
PARCEL 6 FINAL SIC - LOT 6081-2024-07-16_V1.PDF DOCUMENTS VIEW
Z370 ROOSEVELT- TRUSS REVIEW LETTER - LAYOUT (STAMPED)_V1.PDF DOCUMENTS VIEW
BLOCK 6 LOT 81 PLOT PLAN (2 REVISION)_V1.PDF DOCUMENTS VIEW
REVISION NARRATIVE (10-3-2023)_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BLOCK 6 LOT 81 PLOT PLAN (REVISED)_V1.PDF DOCUMENTS VIEW
REVISION EXPLANATION (BLOCK 6)_V1.PDF DOCUMENTS VIEW