Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address:
5906 E JAYDEN LN
Address NEW:
5906 E JAYDEN LN
Apply Date:
06/30/2025
Applicant:
Candis Benson
Description:
New Residential Model Plan (Model master plan TC-MDP-1224-01415)

Permit Reviews

Permit Number - TC-MDP-0225-00114
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415)
Start Date Submittal Complete Date Status  
07/02/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 07/08/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0225-00114
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415)
Total Outstanding Activity Conditions - 5
Date Name
02/07/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
07/02/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/02/2025 Post-Installed Anchor Inspection Report is required.
07/02/2025 Post-Tension Inspection Report is required.
07/02/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.

Conditions

Permit Number - TC-MDP-0225-00114
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415)
Date Description Comments
02/07/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
02/07/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0225-00114
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415)
Total Completed Inspections - 22
Date Description Inspector Results Comments
07/24/2025 COT - RSPL - Backwater Valve Passed 7.24.25
Rough plumbing system is installed according to plan and per code. Proper fittings and pipe sizes verified throughout. 10ft head of water verified for pipes under test. Tracer wires present. Backwater valve in place. Trench conditions acceptable. Ok to backfill.
07/24/2025 COT - RSPL - Rough Soil Passed
07/24/2025 COT - RSPL - Sewer Passed 7.24.25
Rough plumbing system is installed according to plan and per code. Proper fittings and pipe sizes verified throughout. 10ft head of water verified for pipes under test. Tracer wires present. Backwater valve in place. Trench conditions acceptable. Ok to backfill.
07/24/2025 COT - RSPL - Yard Water Line Passed 7.24.25
Rough plumbing system is installed according to plan and per code. Proper fittings and pipe sizes verified throughout. 10ft head of water verified for pipes under test. Tracer wires present. Backwater valve in place. Trench conditions acceptable. Ok to backfill.
07/28/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 7.28.25
Footer depth verified. Rebar size, placement and clearance verified. Uffer verified. Hold downs verified per plan. Ok to pour
07/28/2025 COT - RSBU - Preslab Passed 7.28.25
Footer depth verified. Rebar size, placement and clearance verified. Uffer verified. Hold downs verified per plan. Ok to pour
07/28/2025 COT - RSEL - Electrical Underground Passed 7.28.25
Verified per plan and per code
08/11/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 8.11.25
Rsp4s verified
H25 verified
A35 verified
Anchor bolts verified
Shot pins verified
Straps verified
Fastener schedule verified at sheathing
Roof nailing verified
Truss schedule verified
Bracing verified
Approved
08/11/2025 COT - RSBU - Roof Nailing Passed approved
08/25/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
08/25/2025 COT - RSEL - Grounding/Bonding Passed
08/25/2025 COT - RSPL - Gas Pressure Test Passed
09/03/2025 COT - RSBU - Interior Shear Bracing Passed 9.3.2025
Nail schedule per plan.
09/08/2025 BULD - Electrical Clearance Passed 9/8/25:Ok to set meters . Code: ECO
10/15/2025 COT - BULD - SWG Clearance Passed
10/24/2025 COT - RSEL - Electrical Final Passed
10/24/2025 COT - RSEL - Outdoor Lighting Passed
10/24/2025 COT - RSME - Mechanical Final Passed
10/24/2025 COT - RSPL - Plumbing Final Passed
10/24/2025 ENGR Engineering Final Passed Site is complete in accordance with approved plans. Engineering is okay for CofO.
10/24/2025 RSBU - Building Final Passed
10/24/2025 RSBU - Building Progress Passed