Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9835 E GRAY HAWK DR
Apply Date:
02/05/2025
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)

Permit Reviews

Permit Number - TC-MDP-0225-00082
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Start Date Submittal Complete Date Status  
04/21/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/21/2025 REQUIRES RESUBMIT Review Details
02/07/2025 SITE FROM MODEL PERMIT - PRODUCTION v.1 02/15/2025 REQUIRES RESUBMIT Review Details
05/16/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 05/19/2025 APPROVED Review Details
02/19/2025 SITE FROM MODEL PERMIT - PRODUCTION v.2 02/19/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0225-00082
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Outstanding Activity Conditions - 1
Date Name
02/03/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Conditions

Permit Number - TC-MDP-0225-00082
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Date Description Comments
02/03/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
02/07/2025 Post-Installed Anchor Inspection Report is required.
02/07/2025 Post-Tension Inspection Report is required.
02/03/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
02/07/2025 Soil Testing Special Inspection is Required.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0225-00082
Permite Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
03/26/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required Caulk penetrations at marked areas in vapor barrier

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0225-00082
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/26/2025 COT - RSPL - Backwater Valve Passed
02/26/2025 COT - RSPL - Rough Soil Passed
02/26/2025 COT - RSPL - Sewer Passed
02/26/2025 COT - RSPL - Yard Water Line Passed
03/05/2025 BULD - Electrical Clearance Passed PASSED 3/5/25 CLEARANCE ECO
03/05/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 3/5/25 Ok to pour concrete
03/05/2025 COT - RSBU - Preslab Passed Passed 3/5/25 Ok to pour concrete
03/05/2025 COT - RSEL - Electrical Underground Passed Passed 3/5/25 Ok to pour concrete
03/05/2025 COT - RSEL - Grounding/Bonding Passed Passed 3/5/25 Ok to pour concrete
03/14/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
03/14/2025 COT - RSBU - Roof Nailing Passed
03/26/2025 COT - RSPL - Gas Pressure Test Passed Passed 3/26/25 held pressure
03/27/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 27 March 25
Pass
03/27/2025 RSBU - Building Progress Passed
04/03/2025 COT - RSBU - Interior Shear Bracing Passed
05/13/2025 COT - BULD - SWG Clearance Passed Passed CLEARANCE SWG 5/13/25
05/20/2025 RSBU - Building Final Passed 5/20/25 passed final
05/20/2025 COT - RSPL - Plumbing Final Passed 5/20/25 passed final
05/20/2025 COT - RSME - Mechanical Final Passed 5/20/25 passed final
05/20/2025 COT - RSEL - Outdoor Lighting Passed 5/20/25 passed final
05/20/2025 COT - RSEL - Electrical Final Passed 5/20/25 passed final
05/21/2025 ENGR Engineering Final Passed Site is clean and clear and in accordance with approved plans. CofO ready.

Documents

File Name Document Type  
CDC 20 SIC-2025-05-14_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 20 D1_V1.PDF DOCUMENTS VIEW
CDC 20 SIC-2025-02-05_V1.PDF DOCUMENTS VIEW