Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0224-00252
Permit Details
Apply Date:
03/29/2024
Applicant:
Daria Hopkins
Description:
SFR MERI132021 T21-M0062
Permit Reviews
Permit Number - TC-MDP-0224-00252
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/09/2024 | APPROVED |
04/01/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0224-00252
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
02/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/03/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
04/03/2024 | Post-Tension Inspection Report is required. |
04/03/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0224-00252
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Date | Description | Comments |
---|---|---|
02/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0224-00252
Permit Description: SFR MERI132021 T21-M0062
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/24/2024 | COT - RSPL - Rough Soil | Passed | 10-24-24, underground plumbing per approved plans. Okay to backfill. | |
10/24/2024 | COT - RSPL - Sewer | Passed | 10-24-24, Sewer connection per approved plans. Okay to backfill. | |
10/24/2024 | COT - RSPL - Yard Water Line | Passed | 10-24-24, Main water line per approved plans. Okay to backfill. | |
11/01/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11-1-24, setbacks verified per approved plans. | |
11/01/2024 | COT - RSBU - Preslab | Passed | 11-1-24, preslab per approved plans. Okay to pour concrete. | |
11/01/2024 | COT - RSEL - Electrical Underground | Passed | 11-1-24, approved. | |
11/01/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-1-24, grounding/bonding inspection per approved plans. Okay to pour concrete. | |
11/13/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 11-13-24, exterior clips/sheathing per approved plans. Okay to continue construction | |
11/13/2024 | COT - RSBU - Roof Nailing | Passed | 11-13-24, exterior clips/sheathing and roof nailing per approved plans. Okay to continue construction |