Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
6433 S AMBARELLA DR
Apply Date:
03/05/2024
Applicant:
Celina Rodriguez
Description:
VC 1465-130

Permit Reviews

Permit Number - TC-MDP-0224-00204
Permit Status: Inspections complete
Permit Description: VC 1465-130
Start Date Submittal Complete Date Status  
03/05/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 03/15/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0224-00204
Permit Status: Inspections complete
Permit Description: VC 1465-130
Total Outstanding Activity Conditions - 7
Date Name
02/09/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
03/15/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
03/15/2024 Post-Installed Anchor Inspection Report is required.
03/15/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
03/15/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
04/03/2023 Post-Tension Inspection Report is required.
04/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0224-00204
Permit Status: Inspections complete
Permit Description: VC 1465-130
Date Description Comments
03/15/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
02/09/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00204
Permit Description: VC 1465-130
Total Completed Inspections - 21
Date Description Inspector Results Comments
03/28/2024 COT - RSPL - Sewer Passed
03/28/2024 COT - RSPL - Rough Soil Passed
04/23/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
04/23/2024 COT - RSBU - Preslab Passed
04/23/2024 COT - RSEL - Electrical Underground Passed
04/23/2024 COT - RSPL - Yard Water Line Passed
04/23/2024 COT - RSEL - Grounding/Bonding Passed
05/01/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/01/2024 COT - RSBU - Roof Nailing Passed
05/13/2024 BULD - Electrical Clearance Passed
05/16/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/16/2024 COT - RSPL - Gas Pressure Test Passed
05/23/2024 COT - RSBU - Interior Shear Bracing Passed
07/05/2024 COT - BULD - SWG Clearance Passed SWG for meter only
07/22/2024 COT - RSEL - Electrical Final Passed
07/22/2024 COT - RSEL - Outdoor Lighting Passed
07/22/2024 COT - RSME - Mechanical Final Passed
07/22/2024 COT - RSPL - Plumbing Final Passed
07/22/2024 ENGR Engineering Final Passed Again now way of knowing if lot has positive drainage.
Tree needs to be tied correctly and remove the nursery stakes
07/22/2024 RSBU - Building Final Passed
07/22/2024 RSBU - Building Progress Passed