Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0224-00197
Permit Details
Apply Date:
02/08/2024
Applicant:
Joshua Swinney
Description:
Black Mountain model SFR Escalara
Permit Reviews
Permit Number - TC-MDP-0224-00197
Permit Status: Inspections complete
Permit Description: Black Mountain model SFR Escalara
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2024 | APPROVED |
02/08/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/26/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0224-00197
Permit Status: Inspections complete
Permit Description: Black Mountain model SFR Escalara
Date | Description | Comments |
---|---|---|
02/26/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
02/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
02/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
01/20/2023 | Post-Tension Inspection Report is required. | |
10/21/2024 | Post-Tension Inspection Report is required. | |
02/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
12/12/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
02/08/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
12/12/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
02/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
01/20/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
04/19/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00197
Permite Description: Black Mountain model SFR Escalara
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/06/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
08/06/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00197
Permit Description: Black Mountain model SFR Escalara
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2024 | COT - RSPL - Backwater Valve | Passed | ||
04/19/2024 | COT - RSPL - Rough Soil | Passed | ||
04/19/2024 | COT - RSPL - Yard Water Line | Passed | ||
05/03/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is installed per plans, rebar reinforcement is in place per plans, shear wall straps are installed per plans, masa clips are installed and spaced properly on forms, all plumbing pipes are properly wrapped for protection, and Ufer ground is installed on garage side of house. Okay to pour concrete for footings and slab. | |
05/03/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is installed per plans, rebar reinforcement is in place per plans, shear wall straps are installed per plans, masa clips are installed and spaced properly on forms, all plumbing pipes are properly wrapped for protection, and Ufer ground is installed on garage side of house. Okay to pour concrete for footings and slab. | |
05/03/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is installed per plans, rebar reinforcement is in place per plans, shear wall straps are installed per plans, masa clips are installed and spaced properly on forms, all plumbing pipes are properly wrapped for protection, and Ufer ground is installed on garage side of house. Okay to pour concrete for footings and slab. | |
05/03/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are set, post tension cabling is installed per plans, rebar reinforcement is in place per plans, shear wall straps are installed per plans, masa clips are installed and spaced properly on forms, all plumbing pipes are properly wrapped for protection, and Ufer ground is installed on garage side of house. Okay to pour concrete for footings and slab. | |
06/07/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
06/07/2024 | COT - RSBU - Roof Nailing | Passed | ||
08/13/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 8/13/2024. Corrections were made. | |
08/23/2024 | COT - RSBU - Interior Shear Bracing | Passed | Drywall is properly installed and screwed to studs per the plan requirements for an interior shear braced walls. | |
09/17/2024 | COT - RSPL - Sewer | Passed | ||
09/17/2024 | RSBU - Building Progress | Passed | 9/17/24: 18 inches of copper top and bottom before sweat joint outside of wall main water line | |
10/30/2024 | BULD - Electrical Clearance | Passed | 10-30-24, panel approved for power. | |
11/21/2024 | COT - RSEL - Electrical Final | Passed | 11-21-24, mechanical, electrical, outdoor lighting, plumbing and building final approved. | |
11/21/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-21-24, mechanical, electrical, outdoor lighting, plumbing and building final approved. | |
11/21/2024 | COT - RSME - Mechanical Final | Passed | 11-21-24, mechanical, electrical, outdoor lighting, plumbing and building final approved. | |
11/21/2024 | COT - RSPL - Plumbing Final | Passed | 11-21-24, mechanical, electrical, outdoor lighting, plumbing and building final approved. | |
11/21/2024 | ENGR Engineering Final | Passed | Replace DG now sidewalk forms are removed. | |
11/21/2024 | RSBU - Building Final | Passed | 11-21-24, mechanical, electrical, outdoor lighting, plumbing and building final approved. |