Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
02/05/2024
Applicant:
Christi Swenson
Description:
SFR PULT3515-3 T21-M0047

Permit Reviews

Permit Number - TC-MDP-0224-00170
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
Start Date Submittal Complete Date Status  
03/07/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 03/19/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0224-00170
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
Total Outstanding Activity Conditions - 6
Date Name
02/05/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
03/18/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/18/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
03/18/2024 Post-Tension Inspection Report is required.
03/18/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
03/18/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0224-00170
Permit Status: Inspections complete
Permit Description: SFR PULT3515-3 T21-M0047
Date Description Comments
02/05/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00170
Permite Description: SFR PULT3515-3 T21-M0047
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
07/18/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 7/18/24: register in master bedroom not blocked on three sides. Roof not loaded.
07/18/2024 COT - RSPL - Gas Pressure Test N/A Re-inspection required 7/18/24: no pressure gauge on gas line.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00170
Permit Description: SFR PULT3515-3 T21-M0047
Total Completed Inspections - 21
Date Description Inspector Results Comments
05/03/2024 COT - RSPL - Rough Soil Passed
05/03/2024 COT - RSPL - Sewer Passed
05/03/2024 COT - RSPL - Yard Water Line Passed
05/09/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
05/09/2024 COT - RSBU - Preslab Passed
05/09/2024 COT - RSEL - Electrical Underground Passed
06/14/2024 COT - RSBU - Roof Nailing Passed
06/17/2024 COT - RSBU - Exterior Clips/Sheathing Passed
07/23/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Corrections were made. 7/23/2024
07/23/2024 COT - RSPL - Gas Pressure Test Passed Corrections were made. 7/23/2024
07/23/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. 7/23/2024
07/23/2024 COT - RSEL - Grounding/Bonding Passed
07/29/2024 COT - RSBU - Interior Shear Bracing Passed
09/16/2024 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 9/16/2024
10/03/2024 ENGR Engineering Final Passed CO Ready
10/25/2024 COT - RSEL - Electrical Final Passed 10-25-24, listed items from previous inspection have been corrected. Building final inspected approved.
10/25/2024 COT - RSEL - Outdoor Lighting Passed 10-25-24, listed items from previous inspection have been corrected. Building final inspected approved.
10/25/2024 COT - RSME - Mechanical Final Passed 10-25-24, listed items from previous inspection have been corrected. Building final inspected approved.
10/25/2024 COT - RSPL - Plumbing Final Passed 10-25-24, listed items from previous inspection have been corrected. Building final inspected approved.
10/25/2024 RSBU - Building Final Passed 10-25-24, listed items from previous inspection have been corrected. Building final inspected approved.
10/25/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW