Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Model Building Permit
Apply Date:
02/12/2024
Applicant:
Paula Hinman
Description:
Blackhawk T934 - Frasier

Permit Reviews

Permit Number - TC-MDP-0224-00157
Permit Status: Issued
Permit Description: Blackhawk T934 - Frasier
Start Date Submittal Complete Date Status  
02/12/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 02/16/2024 APPROVED Review Details
06/04/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/04/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0224-00157
Permit Status: Issued
Permit Description: Blackhawk T934 - Frasier
Date Description Comments
02/12/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/16/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
02/12/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/16/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/04/2024 Post-Tension Inspection Report is required.
09/25/2023 Post-Tension Inspection Report is required.
12/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
02/01/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
12/22/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
06/04/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
09/25/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0224-00157
Permit Description: Blackhawk T934 - Frasier
Total Completed Inspections - 22
Date Description Inspector Results Comments
03/11/2024 COT - RSPL - Backwater Valve Passed 3/11/24: Underground plumbing is connected to backwater valve and main sewer. Entire system is under a 10' water test with no leaks detected. Okay to shade pipe and backfill trenches.
03/11/2024 COT - RSPL - Rough Soil Passed 3/11/24: Underground plumbing is connected to backwater valve and main sewer. Entire system is under a 10' water test with no leaks detected. Okay to shade pipe and backfill trenches.
03/11/2024 COT - RSPL - Sewer Passed 3/11/24: Underground plumbing is connected to backwater valve and main sewer. Entire system is under a 10' water test with no leaks detected. Okay to shade pipe and backfill trenches.
03/11/2024 COT - RSPL - Yard Water Line Passed 3/11/24: Partial Pass--Main water line is installed in trench with blue tracer wire. Water is not connected to the main because no meter has been supplied.
03/13/2024 COT - RSEL - Electrical Underground Passed
03/14/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
03/14/2024 COT - RSBU - Preslab Passed
03/22/2024 COT - RSBU - Exterior Clips/Sheathing Passed Some anchor bolts missing east wall ok to continue can check at intermediate
03/22/2024 COT - RSBU - Roof Nailing Passed
04/05/2024 BULD - Electrical Clearance Passed
04/05/2024 COT - RSPL - Gas Pressure Test Passed
04/05/2024 COT - RSEL - Grounding/Bonding Passed
04/09/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
04/09/2024 RSBU - Building Progress Passed
04/18/2024 COT - RSBU - Interior Shear Bracing Passed
05/24/2024 COT - BULD - SWG Clearance Passed
05/28/2024 COT - RSEL - Electrical Final Passed
05/28/2024 COT - RSEL - Outdoor Lighting Passed
05/28/2024 COT - RSME - Mechanical Final Passed
05/28/2024 COT - RSPL - Plumbing Final Passed
05/28/2024 ENGR Engineering Final Passed
05/28/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
146249 PT LOT 80 COMPLETE-2024-06-04_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BLACKHAWK RANCH PLOT PLAN_ LOT 80 START_6122 E CAMPOLINA TRAIL_V1.PDF DOCUMENTS VIEW
TC-MDP-0923-01490 BLACKHAWK LOT 80- T934_ SIC-6122 E CAMPOLINA TRAIL-2024-02-12_V1.PDF DOCUMENTS VIEW