Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0223-00523
Permit Details
Apply Date:
10/19/2023
Applicant:
Daria Hopkins
Description:
SFR MER2302690 T21-M0069
Permit Reviews
Permit Number - TC-MDP-0223-00523
Permit Status: Complete
Permit Description: SFR MER2302690 T21-M0069
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/19/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/23/2023 | APPROVED |
09/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/26/2024 | APPROVED |
02/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/07/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0223-00523
Permit Status: Complete
Permit Description: SFR MER2302690 T21-M0069
Date | Description | Comments |
---|---|---|
10/19/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
10/19/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/19/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
02/07/2024 | Post-Tension Inspection Report is required. | |
10/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
09/26/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
10/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
09/26/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
09/26/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0223-00523
Permit Description: SFR MER2302690 T21-M0069
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/14/2023 | COT - RSPL - Rough Soil | Passed | ||
12/14/2023 | COT - RSPL - Yard Water Line | Passed | ||
12/22/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
12/22/2023 | COT - RSBU - Preslab | Passed | ||
12/22/2023 | COT - RSEL - Electrical Underground | Passed | ||
12/22/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
12/22/2023 | COT - RSPL - Backwater Valve | Passed | ||
01/24/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
01/25/2024 | COT - RSBU - Roof Nailing | Passed | ||
02/23/2024 | BULD - Electrical Clearance | Passed | TEP eco | |
02/23/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
02/29/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/13/2024 | COT - RSPL - Sewer | Passed | ||
03/19/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
04/30/2024 | COT - BULD - SWG Clearance | Passed | ||
05/21/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
05/21/2024 | COT - RSME - Mechanical Final | Passed | ||
05/21/2024 | RSBU - Building Progress | Passed | ||
05/29/2024 | COT - RSEL - Electrical Final | Passed | 5/29/24: Above items have been corrected. Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled, GFCI & AFCI breakers are installed for all required electrical outlets. Okay to issue Certificate of Occupancy once other agencies perform and pass their inspections. | |
05/29/2024 | COT - RSPL - Plumbing Final | Passed | 5/29/24: Above items have been corrected. Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled, GFCI & AFCI breakers are installed for all required electrical outlets. Okay to issue Certificate of Occupancy once other agencies perform and pass their inspections. | |
05/29/2024 | RSBU - Building Final | Passed | 5/29/24: Above items have been corrected. Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled, GFCI & AFCI breakers are installed for all required electrical outlets. Okay to issue Certificate of Occupancy once other agencies perform and pass their inspections. | |
05/29/2024 | ENGR Engineering Final | Passed |