Permit: TC-MDP-0223-00497
Permit Details
Apply Date:
04/18/2023
Applicant:
Daria Hopkins
Description:
SFR MERI192021 T21-M0064
Permit Reviews
Permit Number - TC-MDP-0223-00497
Permit Status: Complete
Permit Description: SFR MERI192021 T21-M0064
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/08/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/08/2024 | APPROVED |
04/19/2023 | RESIDENTIAL NEW DWELLING v.1 | 04/25/2023 | APPROVED |
04/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/02/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0223-00497
Permit Status: Complete
Permit Description: SFR MERI192021 T21-M0064
Date | Description | Comments |
---|---|---|
04/19/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
04/19/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/19/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
04/02/2024 | Post-Tension Inspection Report is required. | |
04/19/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/02/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
06/15/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
04/19/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
04/19/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0223-00497
Permite Description: SFR MERI192021 T21-M0064
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/16/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | Dwv not under test, block registers on all 3 sides at second floor, tubs/showers not under test. 8/16/23 shower not under test, gas line at kitchen needs to be supported or braced. No movement is allowed. |
12/13/2023 | ENGR Engineering Final | N/A | Canceled |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0223-00497
Permit Description: SFR MERI192021 T21-M0064
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2023 | COT - RSPL - Yard Water Line | Passed | ||
06/17/2023 | COT - RSPL - Sewer | Passed | ||
06/17/2023 | COT - RSPL - Rough Soil | Passed | ||
06/17/2023 | COT - RSPL - Backwater Valve | Passed | ||
06/28/2023 | COT - RSBU - Preslab | Passed | Rebar reinforcement is in place at footings. Post tension cables are installed per plans. Shear wall braces and base plate clips are installed per plans. Okay to pour concrete for footings and slab on grade. | |
06/28/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Rebar reinforcement is in place at footings. Post tension cables are installed per plans. Shear wall braces and base plate clips are installed per plans. Okay to pour concrete for footings and slab on grade. | |
06/28/2023 | COT - RSEL - Electrical Underground | Passed | Ufer ground is in place within footing. Okay to pour concrete footing and slab on grade. | |
06/28/2023 | COT - RSEL - Grounding/Bonding | Passed | Ufer ground is in place within footing. Okay to pour concrete footing and slab on grade. | |
07/11/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/11/2023 | COT - RSBU - Roof Nailing | Passed | ||
08/14/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
08/25/2023 | BULD - Electrical Clearance | Passed | ||
10/17/2023 | COT - BULD - SWG Clearance | Passed | Approved, SWG clearance is required for the new meter | |
11/03/2023 | COT - RSEL - Electrical Final | Passed | ||
11/03/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
11/03/2023 | COT - RSME - Mechanical Final | Passed | ||
11/03/2023 | COT - RSPL - Gas Final | Passed | ||
11/03/2023 | COT - RSPL - Plumbing Final | Passed | ||
11/03/2023 | RSBU - Building Final | Passed | ||
04/02/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
04/02/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
04/02/2024 | RSBU - Building Progress | Passed | ||
04/02/2024 | ENGR Engineering Final | Passed | Electrical panel locked so no indication of a passed grade cert. Everything else looks good. |