Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0223-00489
Permit Details
Apply Date:
02/03/2023
Applicant:
Daria Hopkins
Description:
SFR 130.1600 T21-M0030
Permit Reviews
Permit Number - TC-MDP-0223-00489
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/07/2023 | RESIDENTIAL NEW DWELLING v.1 | 02/08/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0223-00489
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
02/08/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
02/08/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
02/08/2023 | Post-Tension Inspection Report is required. |
02/08/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0223-00489
Permite Description: SFR 130.1600 T21-M0030
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/01/2023 | COT - RSBU - Exterior Clips/Sheathing | N/A | Not Ready | Add anchor bolts were needed. 5/1/2023 |
05/01/2023 | COT - RSBU - Roof Nailing | N/A | Not Ready | Check tails for nailing and loose roof panels. 5/1/2023 |
06/05/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
08/30/2023 | RSBU - Building Final | N/A | Re-inspection required | 8/30/23:Properly secure ac unit disconnect box exterior |
08/30/2023 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 8/30/23:Properly secure ac unit disconnect box exterior |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0223-00489
Permit Description: SFR 130.1600 T21-M0030
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/06/2023 | COT - RSPL - Sewer | Passed | ||
04/06/2023 | COT - RSPL - Rough Soil | Passed | ||
04/19/2023 | RSBU - Building Progress | Passed | pre-slab inspection: post-tension cabling is in place. shear wall straps are in place. subsoil is compacted. okay to pour concrete slab. | |
05/01/2023 | COT - RSPL - Yard Water Line | Passed | Approved 5/1/2023 | |
05/01/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Approved per Ralph M. See building progress notes. 5/1/2023 | |
05/01/2023 | COT - RSBU - Preslab | Passed | Approved per Ralph M. See building progress notes. 5/1/2023 | |
05/01/2023 | COT - RSEL - Electrical Underground | Passed | Approved per Ralph M. See building progress notes. 5/1/2023 | |
05/01/2023 | COT - RSEL - Grounding/Bonding | Passed | Approved per Ralph M. See building progress notes. 5/1/2023 | |
05/03/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
05/03/2023 | COT - RSBU - Roof Nailing | Passed | ||
06/05/2023 | BULD - Electrical Clearance | Passed | ||
06/05/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
06/21/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/10/2023 | COT - RSBU - Interior Shear Bracing | Passed | Interior shear walls are properly screwed off. Okay to begin tape and texture of drywall. | |
08/22/2023 | COT - BULD - SWG Clearance | Passed | Swg clearance for meter only. | |
08/30/2023 | COT - RSEL - Electrical Final | Passed | ||
08/30/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
08/30/2023 | COT - RSPL - Gas Final | Passed | ||
08/30/2023 | COT - RSPL - Plumbing Final | Passed | ||
09/01/2023 | RSBU - Building Final | Passed | ||
09/01/2023 | COT - RSME - Mechanical Final | Passed |