Permit: TC-MDP-0126-00007
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
5954 E GABILAN LN
Address NEW:
5954 E GABILAN LN
Apply Date:
04/03/2026
Applicant:
Candis Benson
Description:
Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385) Rev 1
Permit Reviews
Permit Number - TC-MDP-0126-00007
Permit Status: Inspections complete
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385) Rev 1
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/06/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 04/15/2026 | APPROVED |
| 07/24/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/27/2026 | APPROVED |
Conditions
Permit Number - TC-MDP-0126-00007
Permit Status: Inspections complete
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385) Rev 1
| Date | Description | Comments |
|---|---|---|
| 04/08/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/08/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 01/09/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/09/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/09/2026 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 04/08/2026 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 01/09/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0126-00007
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385) Rev 1
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2026 | COT - RSPL - Backwater Valve | Passed | ||
| 05/04/2026 | COT - RSPL - Rough Soil | Passed | 05/04/2026 All fixtures holding under test. Okay to backfill, shading required. |
|
| 05/04/2026 | COT - RSPL - Sewer | Passed | 05/04/2026 Holding under test to HCS. Okay to backfill, shading required. |
|
| 05/04/2026 | COT - RSPL - Yard Water Line | Passed | 05/04/2026 Holding under test to meter. Okay to backfill, shading required. |
|
| 05/08/2026 | BULD - Electrical Clearance | Passed | 05/08/2026 Clearance TEP INCR. |
|
| 05/08/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 05/08/2026 Approved per plan, ok to pour. |
|
| 05/08/2026 | COT - RSBU - Preslab | Passed | 05/08/2026 Approved per plan, ok to pour. |
|
| 05/08/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 05/19/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 5.19.26 Approved |
|
| 05/19/2026 | COT - RSBU - Roof Nailing | Passed | 5.19.26 Approved |
|
| 06/02/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/02/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 06/25/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/27/2026 | COT - BULD - SWG Clearance | Passed | 7-27-26 SWG Clearance approved | |
| 08/06/2026 | COT - RSEL - Electrical Final | Passed | 8-6-26: electrical final approved. | |
| 08/06/2026 | COT - RSEL - Outdoor Lighting | Passed | 8-6-26: approved. | |
| 08/06/2026 | COT - RSME - Mechanical Final | Passed | 8-6-26: mechanical final approved. | |
| 08/06/2026 | COT - RSPL - Plumbing Final | Passed | 8-6-26: plumbing final approved. | |
| 08/06/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 08/06/2026 | RSBU - Building Progress | Passed | 8-6-26: approved. | |
| 08/13/2026 | RSBU - Building Final | Passed | IHD waiver authorized for this site. |