Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
01/21/2025
Applicant:
Candis Benson
Description:
SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)

Permit Reviews

Permit Number - TC-MDP-0125-00053
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Start Date Submittal Complete Date Status  
04/18/2025 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/28/2025 REQUIRES RESUBMIT Review Details
04/28/2025 SITE FROM MODEL PERMIT - PRODUCTION v.2 04/28/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0125-00053
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Total Outstanding Activity Conditions - 4
Date Name
01/28/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
04/28/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/28/2025 Post-Installed Anchor Inspection Report is required.
04/28/2025 Post-Tension Inspection Report is required.

Conditions

Permit Number - TC-MDP-0125-00053
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Date Description Comments
01/28/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
01/28/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0125-00053
Permite Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
06/16/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 6-16-25: missing several RSP4's on north side, add nails to overpenetrated sheathing along edges of garage, add shot pins at marked locations, add nails at bedroom 3 shear wall along edge/joint, install a larger cs strap with 10 nails above/below interconnecting points from beam to post (both sides of back patio), missing wall bracing/parallel at bedroom 2 and dining room area-see detail S5.2-12.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0125-00053
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4) (Model master plan TC-MDP-1222-00031)
Total Completed Inspections - 21
Date Description Inspector Results Comments
05/19/2025 COT - RSPL - Rough Soil Passed Passed 5/19/25 ok to backfill
05/19/2025 COT - RSPL - Sewer Passed Passed 5/19/25 ok to backfill
05/19/2025 COT - RSPL - Yard Water Line Passed Passed 5/19/25 ok to backfill
05/23/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 5/23/25 ok to pour concrete
05/23/2025 COT - RSBU - Preslab Passed Passed 5/23/25 ok to pour concrete
05/23/2025 COT - RSEL - Electrical Underground Passed Passed 5/23/25 ok to pour concrete
06/16/2025 COT - RSBU - Roof Nailing Passed 6-16-25: roof nailing approved. Okay to dry-in.
06/23/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 6/23/25 corrections made
07/07/2025 BULD - Electrical Clearance Passed Passed 7/7/25 CLEARANCE ECO
07/07/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 7/7/25
07/07/2025 COT - RSEL - Grounding/Bonding Passed Passed 7/7/25
07/07/2025 COT - RSPL - Gas Pressure Test Passed Passed 7/7/25
07/15/2025 COT - RSBU - Interior Shear Bracing Passed Passed 7/25/25
09/05/2025 COT - BULD - SWG Clearance Passed 9.5.2025
Clearance for SW Gas.
09/11/2025 COT - RSEL - Electrical Final Passed 9.11.25
Approved
09/11/2025 COT - RSEL - Outdoor Lighting Passed 9.11.25
Approved
09/11/2025 COT - RSME - Mechanical Final Passed 9.11.25
Approved
09/11/2025 COT - RSPL - Plumbing Final Passed 9.11.25
Approved
09/11/2025 ENGR Engineering Final Passed
09/11/2025 RSBU - Building Final Passed 9.11.25
Approved
09/11/2025 RSBU - Building Progress Passed 9.11.25
Approved

Documents

File Name Document Type  
1_SITEPLAN_V1 (1).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2025-04-17_V1.PDF DOCUMENTS VIEW