Permit: TC-MDP-0125-00047
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
5923 E JAYDEN LN
Address NEW:
5923 E JAYDEN LN
Apply Date:
04/27/2025
Applicant:
mark wolfel
Description:
Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385)
Permit Reviews
Permit Number - TC-MDP-0125-00047
Permit Status: Inspections complete
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/01/2025 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/12/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0125-00047
Permit Status: Inspections complete
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385)
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/28/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 05/02/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 05/02/2025 | Post-Installed Anchor Inspection Report is required. |
| 05/02/2025 | Post-Tension Inspection Report is required. |
| 05/02/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0125-00047
Permit Status: Inspections complete
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385)
| Date | Description | Comments |
|---|---|---|
| 01/28/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 01/28/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0125-00047
Permit Description: Blackhawk B30G New SFR with/AVP (Model master plan TC-MDP-1224-01385)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2025 | COT - RSPL - Rough Soil | Passed | 6-2-25: sewer connection, underground plumbing & main water line approved.Okay to backfill with shading materials. | |
| 06/02/2025 | COT - RSPL - Sewer | Passed | 6-2-25: sewer connection, underground plumbing & main water line approved.Okay to backfill with shading materials. | |
| 06/02/2025 | COT - RSPL - Yard Water Line | Passed | 6-2-25: main water line approved.Okay to backfill. | |
| 06/06/2025 | BULD - Electrical Clearance | Passed | 6-6-25: panel okay to be energized. ECO clearance issued to TEP. | |
| 06/06/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 6-6-25: excavation/reinforcement, setbacks and preslab verified per plans. Okay to pour concrete. | |
| 06/06/2025 | COT - RSBU - Preslab | Passed | 6-6-25: excavation/reinforcement, setbacks and preslab verified per plans. Okay to pour concrete. | |
| 06/06/2025 | COT - RSEL - Electrical Underground | Passed | 6-6-25: electrical underground approved. | |
| 06/17/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 06/17/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 07/01/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 07/01/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/01/2025 | COT - RSPL - Gas Pressure Test | Passed | ||
| 07/15/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed 7/15/25 | |
| 08/19/2025 | COT - BULD - SWG Clearance | Passed | 8.19.25 Verified APPROVED |
|
| 08/27/2025 | COT - RSEL - Electrical Final | Passed | ||
| 08/27/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/27/2025 | COT - RSME - Mechanical Final | Passed | ||
| 08/27/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 08/27/2025 | RSBU - Building Final | Passed | ||
| 08/27/2025 | RSBU - Building Progress | Passed | ||
| 08/28/2025 | ENGR Engineering Final | Passed | CO Ready |