Permit: TC-MDP-0124-00095
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
9123 E RED BLUFF CT
Address NEW:
9123 E RED BLUFF CT
Apply Date:
02/06/2024
Applicant:
Celina Rodriguez
Description:
SFR BT1262-130 T22-M0016
Permit Reviews
Permit Number - TC-MDP-0124-00095
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/06/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/13/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0124-00095
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 01/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 02/06/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 02/06/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 02/13/2024 | Post-Tension Inspection Report is required. |
| 02/13/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 11/22/2023 | THIS DOES NOT APPLY |
Conditions
Permit Number - TC-MDP-0124-00095
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
| Date | Description | Comments |
|---|---|---|
| 01/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 11/22/2023 | THIS DOES NOT APPLY |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0124-00095
Permite Description: SFR BT1262-130 T22-M0016
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/28/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 03/28/2024 | COT - RSEL - Grounding/Bonding | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0124-00095
Permit Description: SFR BT1262-130 T22-M0016
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 03/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 03/28/2024 | COT - RSBU - Preslab | Passed | ||
| 04/17/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 04/19/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 4-19-24: Missing bolts have been installed on both sides of garage door and bedroom #3 shear wall. Nails have been added to RSP Clip at front entry. | |
| 05/10/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 15#of compressed air with no leaks. Okay to proceed. | |
| 05/15/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 5/15/24: all corrections made | |
| 06/14/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/22/2024 | COT - RSPL - Sewer | Passed | Underground plumbing is connected to sewer and under a water pressure test with no leaks in piping or joints. Okay to shade pipe and backfill trench. | |
| 07/22/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing is connected to sewer and under a water pressure test with no leaks in piping or joints. Okay to shade pipe and backfill trench. | |
| 07/24/2024 | BULD - Electrical Clearance | Passed | Okay to energize panel. ECO Clearance issued to TEP for 9123 E. Red Bluff Ct. | |
| 08/08/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 09/17/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 09/17/2024 | ENGR Engineering Final | Passed | ||
| 09/17/2024 | RSBU - Building Progress | Passed | ||
| 09/18/2024 | COT - RSEL - Electrical Final | Passed | ||
| 09/18/2024 | COT - RSME - Mechanical Final | Passed | ||
| 09/18/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 09/18/2024 | RSBU - Building Final | Passed |