Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
2750 S BRANDYWINE LN
Apply Date:
01/11/2024
Applicant:
Chris Irby
Description:
CS1453t (Model Master Plan TC-MDP-0723-01249)

Permit Reviews

Permit Number - TC-MDP-0124-00073
Permit Status: Complete
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
Start Date Submittal Complete Date Status  
01/12/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/26/2024 REQUIRES RESUBMIT Review Details
12/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/05/2025 REQUIRES RESUBMIT Review Details
02/29/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 03/15/2024 APPROVED Review Details
11/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/17/2025 APPROVED Review Details
02/18/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/18/2026 REQUIRES RESUBMIT Review Details
09/24/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/24/2025 REQUIRES RESUBMIT Review Details
02/23/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.3 N/A APPROVED Review Details

Conditions

Permit Number - TC-MDP-0124-00073
Permit Status: Complete
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
Date Description Comments
01/16/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
03/15/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
01/12/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/28/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
01/11/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
09/24/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
01/12/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
01/16/2024 SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED.
07/31/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0124-00073
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
Total Completed Inspections - 22
Date Description Inspector Results Comments
04/28/2025 BULD - Electrical Clearance Passed 4/28/25: TEP ECO CLEARANCE
04/28/2025 COT - RSEL - Electrical Underground Passed
04/28/2025 COT - RSPL - Backwater Valve Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
04/28/2025 COT - RSPL - Sewer Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
04/28/2025 COT - RSPL - Rough Soil Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
04/28/2025 COT - RSPL - Yard Water Line Passed 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required
05/01/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 5/1/25 ready to pour concrete
05/01/2025 COT - RSBU - Preslab Passed Passed 5/1/25 ready to pour concrete
06/12/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 6/12/25 corrections made
06/12/2025 COT - RSBU - Roof Nailing Passed 6/12/25 corrections made
06/12/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 6/12/25
06/12/2025 COT - RSEL - Grounding/Bonding Passed Passed 6/12/25
06/12/2025 COT - RSPL - Gas Pressure Test Passed Passed 6/12/25
06/25/2025 COT - RSBU - Interior Shear Bracing Passed Passed 6/25/25
07/31/2025 COT - BULD - SWG Clearance Passed SWG
08/01/2025 COT - RSEL - Electrical Final Passed
08/01/2025 COT - RSME - Mechanical Final Passed
08/01/2025 COT - RSPL - Plumbing Final Passed
08/01/2025 RSBU - Building Final Passed
08/04/2025 COT - RSEL - Outdoor Lighting Passed passed by Odair
08/04/2025 RSBU - Building Progress Passed passed by Odair
08/07/2025 ENGR Engineering Final Passed Site is safe and accessible. Everything completed in accordance with approved plans.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
RIVENDELL SEWER RELEASE 1-2025-11-12_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SEWERCONNECTIONPERMIT_LOT 25_V1.PDF DOCUMENTS VIEW
RIVENDELL_LOT_25-FINAL RESUBMIT_V2.PDF DOCUMENTS VIEW
LOT 25 - SIC-2024-01-11_V1.PDF DOCUMENTS VIEW