Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
2493 S CLOVIS PL
Address NEW:
2493 S CLOVIS PL
Apply Date:
01/10/2024
Applicant:
Description:
SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32

Permit Reviews

Permit Number - TC-MDP-0124-00062
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Start Date Submittal Complete Date Status  
03/10/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/11/2025 APPROVED Review Details
01/10/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/24/2024 APPROVED Review Details
02/28/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/29/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0124-00062
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Date Description Comments
02/29/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
12/12/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/29/2024 Post-Tension Inspection Report is required.
01/10/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
01/10/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
06/15/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
02/29/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0124-00062
Permite Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
04/08/2024 COT - RSEL - Grounding/Bonding N/A Not Applicable
08/06/2024 COT - BULD - SWG Clearance N/A Not Applicable
08/06/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0124-00062
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Completed Inspections - 19
Date Description Inspector Results Comments
03/20/2024 COT - RSPL - Backwater Valve Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
03/20/2024 COT - RSPL - Yard Water Line Passed Main water supply line is connected to the city water system with a meter. Line is under street pressure with no leaks. Okay to shade pipe and backfill trench.
03/20/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
03/20/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
04/08/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
04/08/2024 COT - RSBU - Preslab Passed
05/24/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/24/2024 COT - RSBU - Roof Nailing Passed
06/17/2024 COT - RSEL - Electrical Underground Passed Sweep and conduit are properly secured to electrical panel and ran out to TEP's transformer. Okay to shade conduit and backfill trench.
06/21/2024 BULD - Electrical Clearance Passed
08/06/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
08/13/2024 COT - RSBU - Interior Shear Bracing Passed
08/15/2024 RSBU - Building Progress Passed
02/03/2025 ENGR Engineering Final Passed
02/07/2025 COT - RSEL - Electrical Final Passed Construction is complete, house is ready for move in. Okay to issue Certificate of Occupancy.
02/07/2025 COT - RSEL - Outdoor Lighting Passed Construction is complete, house is ready for move in. Okay to issue Certificate of Occupancy.
02/07/2025 COT - RSME - Mechanical Final Passed Construction is complete, house is ready for move in. Okay to issue Certificate of Occupancy.
02/07/2025 COT - RSPL - Plumbing Final Passed Construction is complete, house is ready for move in. Okay to issue Certificate of Occupancy.
02/07/2025 RSBU - Building Final Passed Construction is complete, house is ready for move in. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
SI CERT LOT 19.1-2025-03-06_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
PV SITE PLAN-LOT19_V1.PDF DOCUMENTS VIEW
SI CERT LOT 19 2493 S CLOVIS_V1.PDF DOCUMENTS VIEW