Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Model Building Permit
Address:
2494 S CLOVIS PL
Apply Date:
01/10/2024
Applicant:
Description:
SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32

Permit Reviews

Permit Number - TC-MDP-0124-00061
Permit Status: In review
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Start Date Submittal Complete Date Status  
02/28/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/29/2024 APPROVED Review Details
01/10/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/24/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0124-00061
Permit Status: In review
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Outstanding Activity Conditions - 4
Date Name
01/10/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
02/29/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/29/2024 Post-Tension Inspection Report is required.
12/12/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Conditions

Permit Number - TC-MDP-0124-00061
Permit Status: In review
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Date Description Comments
01/10/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-MDP-0124-00061
Permite Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
08/13/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable
08/13/2024 COT - BULD - SWG Clearance N/A Not Applicable

Completed Inspections

Permit Status: In Review
Permit Number: TC-MDP-0124-00061
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Completed Inspections - 14
Date Description Inspector Results Comments
04/25/2024 COT - RSPL - Backwater Valve Passed
04/25/2024 COT - RSPL - Rough Soil Passed
04/25/2024 COT - RSPL - Sewer Passed
04/25/2024 COT - RSPL - Yard Water Line Passed
05/10/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, post tension cabling is installed, underground electrical is in place, Ufer ground is in place on left side of garage, required shear wall hold downs are in place and connected to rebar reinforcement, masa clips are evenly spaced around outside edge of form, and all underground plumbing pipes are wrapped with foam and all bathtub or shower stall drain lines are blocked out properly. Okay to pour concrete for footings and slab on grade.
05/10/2024 COT - RSBU - Preslab Passed Concrete forms are set, post tension cabling is installed, underground electrical is in place, Ufer ground is in place on left side of garage, required shear wall hold downs are in place and connected to rebar reinforcement, masa clips are evenly spaced around outside edge of form, and all underground plumbing pipes are wrapped with foam and all bathtub or shower stall drain lines are blocked out properly. Okay to pour concrete for footings and slab on grade.
05/10/2024 COT - RSEL - Grounding/Bonding Passed Concrete forms are set, post tension cabling is installed, underground electrical is in place, Ufer ground is in place on left side of garage, required shear wall hold downs are in place and connected to rebar reinforcement, masa clips are evenly spaced around outside edge of form, and all underground plumbing pipes are wrapped with foam and all bathtub or shower stall drain lines are blocked out properly. Okay to pour concrete for footings and slab on grade.
06/11/2024 COT - RSBU - Exterior Clips/Sheathing Passed
06/11/2024 COT - RSBU - Roof Nailing Passed
06/17/2024 COT - RSEL - Electrical Underground Passed Sweep and conduit are properly secured to electrical panel and ran out to TEP's transformer. Okay to shade conduit and backfill trench.
06/21/2024 BULD - Electrical Clearance Passed
08/01/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Corrections were made. 8/1/2024
08/13/2024 COT - RSBU - Interior Shear Bracing Passed
08/15/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
PV SITE PLAN-LOT18_V1.PDF DOCUMENTS VIEW
SI CERT LOT 18 2494 S CLOVIS_V1.PDF DOCUMENTS VIEW