Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address:
2373 S CLOVIS PL
Address NEW:
2373 S CLOVIS PL
Apply Date:
01/10/2024
Applicant:
Description:
SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32

Permit Reviews

Permit Number - TC-MDP-0124-00060
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Start Date Submittal Complete Date Status  
02/27/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/29/2024 APPROVED Review Details
04/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/29/2025 APPROVED Review Details
01/10/2024 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/24/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0124-00060
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Date Description Comments
12/12/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/29/2024 Post-Tension Inspection Report is required.
01/10/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0124-00060
Permite Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
04/08/2024 COT - RSEL - Grounding/Bonding N/A Not Applicable
04/17/2025 COT - BULD - SWG Clearance N/A Not Applicable Site does not use gas
04/17/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable Site does not use gas

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0124-00060
Permit Description: SFR PANT2022 T22-M0073 Pantano Vista Lots 1-32
Total Completed Inspections - 19
Date Description Inspector Results Comments
03/20/2024 COT - RSPL - Backwater Valve Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
03/20/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
03/20/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to backwater valve between clean-outs and main sewer line. All pipes are under a water pressure test with no leaks. Okay to shade pipes and backfill trenches.
03/20/2024 COT - RSPL - Yard Water Line Passed Main water supply line is connected to the city water system with a meter. Line is under street pressure with no leaks. Okay to shade pipe and backfill trench.
04/08/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
04/08/2024 COT - RSBU - Preslab Passed
05/20/2024 COT - RSBU - Roof Nailing Passed
05/20/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
06/17/2024 COT - RSEL - Electrical Underground Passed Sweep and conduit are properly secured to electrical panel and ran out to TEP's transformer. Okay to shade conduit and backfill trench.
06/21/2024 BULD - Electrical Clearance Passed
07/18/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
07/30/2024 COT - RSBU - Interior Shear Bracing Passed
12/16/2024 RSBU - Building Progress Passed
04/17/2025 COT - RSEL - Electrical Final Passed Passed final 4/17/25
04/17/2025 COT - RSEL - Outdoor Lighting Passed Passed final 4/17/25
04/17/2025 COT - RSME - Mechanical Final Passed Passed final 4/17/25
04/17/2025 COT - RSPL - Plumbing Final Passed Passed final 4/17/25
04/17/2025 ENGR Engineering Final Passed Site is good. C of O ready.
04/17/2025 RSBU - Building Final Passed Passed final 4/17/25

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
SI CERT LOT 32.1-2025-04-24_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
PV SITE PLAN-LOT32_V1.PDF DOCUMENTS VIEW
SI CERT LOT 32 2373 S CLOVIS_V1.PDF DOCUMENTS VIEW