Permit Details

Status:
Issued
Type:
Model Building Permit
Apply Date:
02/13/2024
Applicant:
Daria Hopkins
Description:
SFR MERI156021 T21-M0063

Permit Reviews

Permit Number - TC-MDP-0124-00051
Permit Status: Issued
Permit Description: SFR MERI156021 T21-M0063
Start Date Submittal Complete Date Status  
02/13/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 02/16/2024 APPROVED Review Details
07/29/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/31/2024 APPROVED Review Details
10/24/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/28/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0124-00051
Permit Status: Issued
Permit Description: SFR MERI156021 T21-M0063
Date Description Comments
02/13/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
02/13/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/13/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/16/2024 Post-Tension Inspection Report is required.
07/31/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
01/09/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
02/13/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
07/31/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0124-00051
Permit Description: SFR MERI156021 T21-M0063
Total Completed Inspections - 21
Date Description Inspector Results Comments
06/09/2024 COT - RSPL - Yard Water Line Passed
06/09/2024 COT - RSPL - Sewer Passed
06/09/2024 COT - RSPL - Rough Soil Passed
06/17/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
06/17/2024 COT - RSBU - Preslab Passed
06/17/2024 COT - RSEL - Electrical Underground Passed
06/17/2024 COT - RSEL - Grounding/Bonding Passed
06/28/2024 COT - RSBU - Roof Nailing Passed
07/11/2024 COT - RSBU - Exterior Clips/Sheathing Passed Corrections were made. 7/11/2024
07/26/2024 COT - RSPL - Gas Pressure Test Passed
07/30/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. 7/30/2024
07/31/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
08/12/2024 COT - RSBU - Interior Shear Bracing Passed
09/25/2024 COT - BULD - SWG Clearance Passed PASSED SW GAS CLEARANCE 9/25/24
10/14/2024 COT - RSEL - Electrical Final Passed Passed final inspection 10/14/24 CLEARANCE ECO
10/14/2024 COT - RSEL - Outdoor Lighting Passed Passed final inspection 10/14/24
10/14/2024 COT - RSME - Mechanical Final Passed Passed final inspection 10/14/24
10/14/2024 COT - RSPL - Plumbing Final Passed Passed final inspection 10/14/24
10/14/2024 ENGR Engineering Final Passed CO Ready
10/14/2024 RSBU - Building Final Passed Passed final inspection 10/14/24
10/14/2024 RSBU - Building Progress Passed Passed final inspection 10/14/24

Documents

File Name Document Type  
148295 PT LOT 22 COMPLETE-2024-07-26_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 22 APPLICATION_V1.PDF DOCUMENTS VIEW
LOT 22 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 22 SPECIAL INSPECTION CERTIFICATE-2024-02-13_V1.PDF DOCUMENTS VIEW