Permit: TC-MDP-0123-00359
Permit Details
Apply Date:
01/25/2023
Applicant:
Celina Rodriguez
Description:
SFR BT2191-30 T22-M0009
Permit Reviews
Permit Number - TC-MDP-0123-00359
Permit Status: Complete
Permit Description: SFR BT2191-30 T22-M0009
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2023 | RESIDENTIAL NEW DWELLING v.1 | 02/16/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0123-00359
Permit Status: Complete
Permit Description: SFR BT2191-30 T22-M0009
Total Outstanding Activity Conditions - 7
Date | Name |
---|---|
02/16/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
02/16/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
02/16/2023 | Post-Installed Anchor Inspection Report is required. |
02/16/2023 | Post-Tension Inspection Report is required. |
02/16/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
06/15/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00359
Permite Description: SFR BT2191-30 T22-M0009
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/01/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | Not ready. Missing anchor bolts behind shear walls and edges of bottom plates. Secure gas line. Laundry circuit is not connected. 2x6 top plate in laundry room needs to be corrected. Duct work is choked. Have separate straps. Tape off connection at cuppling in 1st bathroom. Block at register in bathroom. Nail of girder h25. 5/1/2023 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00359
Permit Description: SFR BT2191-30 T22-M0009
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/17/2023 | COT - RSPL - Yard Water Line | Passed | ||
03/17/2023 | COT - RSPL - Rough Soil | Passed | ||
03/17/2023 | COT - RSPL - Sewer | Passed | ||
03/24/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Post tension cables are in place, compaction is complete. Okay to pour concrete slabs. | |
03/24/2023 | COT - RSBU - Preslab | Passed | 3-24-23: Post tension cables are in place, compaction is complete. Okay to pour concrete slabs. | |
03/24/2023 | COT - RSEL - Electrical Underground | Passed | 3-24-23: Electrical conduit for kitchen island is installed. Okay to pour concrete slab. | |
04/10/2023 | COT - RSBU - Roof Nailing | Passed | ||
04/12/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | Approved. 4/12/2023 | |
05/01/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
05/03/2023 | RSEL - Electrical Progress | Passed | ||
05/03/2023 | RSME - Mechanical Progress | Passed | ||
05/03/2023 | RSPL - Plumbing Progress | Passed | ||
05/03/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
05/04/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
05/15/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
05/25/2023 | BULD - Electrical Clearance | Passed | ||
07/18/2023 | COT - BULD - SWG Clearance | Passed | 7/18/23: SWG meter tag only | |
08/09/2023 | RSBU - Building Final | Passed | ||
08/09/2023 | COT - RSPL - Plumbing Final | Passed | ||
08/09/2023 | COT - RSPL - Gas Final | Passed | ||
08/09/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
08/09/2023 | RSBU - Building Progress | Passed | ||
08/09/2023 | COT - RSME - Mechanical Final | Passed | ||
08/11/2023 | COT - RSEL - Electrical Final | Passed |