Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
01/17/2023
Applicant:
ramon polanco
Description:
SFR BRIOS1432 T20-M0059

Permit Reviews

Permit Number - TC-MDP-0123-00332
Permit Status: Complete
Permit Description: SFR BRIOS1432 T20-M0059
Start Date Submittal Complete Date Status  
01/17/2023 RESIDENTIAL NEW DWELLING v.1 01/19/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0123-00332
Permit Status: Complete
Permit Description: SFR BRIOS1432 T20-M0059
Date Description Comments
01/19/2023 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
01/19/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/19/2023 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
01/19/2023 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
01/19/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00332
Permite Description: SFR BRIOS1432 T20-M0059
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
07/11/2023 BULD - Electrical Clearance N/A Not Ready
12/22/2023 COT - RSEL - Outdoor Lighting N/A Not Applicable
12/27/2023 RSBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00332
Permit Description: SFR BRIOS1432 T20-M0059
Total Completed Inspections - 16
Date Description Inspector Results Comments
02/06/2023 COT - RSPL - Rough Soil Passed
03/02/2023 COT - RSEL - Grounding/Bonding Passed
03/03/2023 COT - RSBU - Preslab Passed
07/27/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
10/11/2023 BULD - Electrical Clearance Passed 10/11/23: ECO TEP Clearance unit #111
12/22/2023 COT - RSBU - Roof Nailing Passed
12/22/2023 COT - RSBU - Interior Shear Bracing Passed
12/22/2023 COT - RSPL - Yard Water Line Passed
12/22/2023 COT - RSEL - Electrical Underground Passed
12/22/2023 COT - RSBU - Exterior Clips/Sheathing Passed
12/22/2023 COT - RSPL - Sewer Passed
12/22/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
12/27/2023 COT - RSME - Mechanical Final Passed
12/27/2023 COT - RSPL - Plumbing Final Passed
12/27/2023 COT - RSEL - Electrical Final Passed
02/20/2024 RSBU - Building Final Passed ok for C OF O

Documents

File Name Document Type  
SIC BLDG 111-2024-02-29_V1.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BUILDING 111 SIC-2023-01-17_V1.PDF DOCUMENTS VIEW
CONS-UTILITY PAGES_V1.PDF DOCUMENTS VIEW