Permit: TC-MDP-0123-00332
Permit Details
Apply Date:
01/17/2023
Applicant:
burak bekat
Description:
SFR BRIOS1432 T20-M0059
Permit Reviews
Permit Number - TC-MDP-0123-00332
Permit Status: Complete
Permit Description: SFR BRIOS1432 T20-M0059
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2023 | RESIDENTIAL NEW DWELLING v.1 | 01/19/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0123-00332
Permit Status: Complete
Permit Description: SFR BRIOS1432 T20-M0059
Date | Description | Comments |
---|---|---|
01/19/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
01/19/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
01/19/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
01/19/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
01/19/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00332
Permite Description: SFR BRIOS1432 T20-M0059
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2023 | BULD - Electrical Clearance | N/A | Not Ready | |
12/22/2023 | COT - RSEL - Outdoor Lighting | N/A | Not Applicable | |
12/27/2023 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00332
Permit Description: SFR BRIOS1432 T20-M0059
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/06/2023 | COT - RSPL - Rough Soil | Passed | ||
03/02/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
03/03/2023 | COT - RSBU - Preslab | Passed | ||
07/27/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
10/11/2023 | BULD - Electrical Clearance | Passed | 10/11/23: ECO TEP Clearance unit #111 | |
12/22/2023 | COT - RSBU - Roof Nailing | Passed | ||
12/22/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
12/22/2023 | COT - RSPL - Yard Water Line | Passed | ||
12/22/2023 | COT - RSEL - Electrical Underground | Passed | ||
12/22/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
12/22/2023 | COT - RSPL - Sewer | Passed | ||
12/22/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
12/27/2023 | COT - RSME - Mechanical Final | Passed | ||
12/27/2023 | COT - RSPL - Plumbing Final | Passed | ||
12/27/2023 | COT - RSEL - Electrical Final | Passed | ||
02/20/2024 | RSBU - Building Final | Passed | ok for C OF O |