Permit: TC-MDP-0123-00314
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
2398 S CLOVIS PL
Address NEW:
2398 S CLOVIS PL
Apply Date:
09/11/2023
Applicant:
Description:
SFR PANT2022 T22-M0073
Permit Reviews
Permit Number - TC-MDP-0123-00314
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/02/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.4 | 11/07/2023 | APPROVED |
| 04/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/25/2025 | APPROVED |
| 09/14/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 09/19/2023 | REQUIRES RESUBMIT |
| 11/07/2023 | RESTAMP - RESIDENTIAL v.1 | 11/07/2023 | APPROVED |
| 10/25/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.3 | 10/26/2023 | REQUIRES RESUBMIT |
| 09/12/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 09/13/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0123-00314
Permit Status: Complete
Permit Description: SFR PANT2022 T22-M0073
| Date | Description | Comments |
|---|---|---|
| 09/12/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 09/12/2023 | Post-Tension Inspection Report is required. | |
| 06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/12/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/15/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 09/12/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00314
Permite Description: SFR PANT2022 T22-M0073
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/26/2023 | COT - RSPL - Yard Water Line | N/A | Canceled | Canceled per wet soils. 12/26/2023 |
| 12/26/2023 | COT - RSPL - Rough Soil | N/A | Canceled | Canceled per wet soils. 12/26/2023 |
| 12/26/2023 | COT - RSPL - Sewer | N/A | Canceled | Canceled per wet soils. 12/26/2023 |
| 04/02/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | site does not use gas |
| 04/02/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | site does not use gas |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0123-00314
Permit Description: SFR PANT2022 T22-M0073
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2023 | COT - RSPL - Yard Water Line | Passed | 12/27/23: Water line is connected to water meter and under pressure from main water supply. Okay to shade pipe and backfill trench. | |
| 12/28/2023 | COT - RSPL - Backwater Valve | Passed | ||
| 12/28/2023 | COT - RSPL - Rough Soil | Passed | ||
| 12/28/2023 | COT - RSPL - Sewer | Passed | ||
| 01/05/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is properly placed, rebar reinforcement is installed at the corners, 20' rebar reinforcement is installed for the Ufer ground, and shear wall straps are installed on both sides of garage. Okay to pour concrete for footings and slab. | |
| 01/05/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is properly placed, rebar reinforcement is installed at the corners, 20' rebar reinforcement is installed for the Ufer ground, and shear wall straps are installed on both sides of garage. Okay to pour concrete for footings and slab. | |
| 01/05/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are set, post tension cabling is properly placed, rebar reinforcement is installed at the corners, 20' rebar reinforcement is installed for the Ufer ground, and shear wall straps are installed on both sides of garage. Okay to pour concrete for footings and slab. | |
| 02/12/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 02/12/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 02/28/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 02/28/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 04/26/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
| 05/02/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 10/03/2024 | RSBU - Building Progress | Passed | ||
| 04/02/2025 | ENGR Engineering Final | Passed | There are a couple nicks in the top of the wedge curb at the right of way that do need to be patched. | |
| 04/02/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed 4/2/25 | |
| 04/02/2025 | COT - RSPL - Plumbing Final | Passed | Passed 4/2/25 | |
| 04/02/2025 | COT - RSME - Mechanical Final | Passed | Passed 4/2/25 | |
| 04/07/2025 | RSBU - Building Final | Passed | Corrections made | |
| 04/15/2025 | COT - RSEL - Electrical Final | Passed | 4-15-25, electrical final approved. |