Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address:
2462 S CLOVIS PL
Apply Date:
10/30/2023
Applicant:
Description:
SFR PANT2022 T22-M0073

Permit Reviews

Permit Number - TC-MDP-0123-00310
Permit Status: Inspections complete
Permit Description: SFR PANT2022 T22-M0073
Start Date Submittal Complete Date Status  
10/30/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 11/03/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0123-00310
Permit Status: Inspections complete
Permit Description: SFR PANT2022 T22-M0073
Total Outstanding Activity Conditions - 2
Date Name
06/15/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
11/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0123-00310
Permit Status: Inspections complete
Permit Description: SFR PANT2022 T22-M0073
Date Description Comments
10/30/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
10/30/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0123-00310
Permite Description: SFR PANT2022 T22-M0073
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
02/19/2025 COT - BULD - SWG Clearance N/A Not Applicable Not required--No gas onsite.
02/19/2025 COT - RSPL - Gas Pressure Test N/A Not Applicable Not required--No gas onsite.
10/22/2024 RSBU - Building Progress N/A Partial Pass called in for permit extension. 10/22/2024

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0123-00310
Permit Description: SFR PANT2022 T22-M0073
Total Completed Inspections - 19
Date Description Inspector Results Comments
01/17/2024 COT - RSPL - Rough Soil Passed
01/17/2024 COT - RSPL - Sewer Passed
01/17/2024 COT - RSPL - Yard Water Line Passed
01/26/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
01/26/2024 COT - RSBU - Preslab Passed
01/26/2024 COT - RSEL - Grounding/Bonding Passed
02/22/2024 COT - RSBU - Exterior Clips/Sheathing Passed
02/22/2024 COT - RSBU - Roof Nailing Passed
02/28/2024 BULD - Electrical Clearance Passed TEP ECO
02/28/2024 COT - RSEL - Electrical Underground Passed
05/17/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation.
05/23/2024 COT - RSBU - Interior Shear Bracing Passed
02/19/2025 COT - RSEL - Electrical Final Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.
02/19/2025 COT - RSEL - Outdoor Lighting Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.
02/19/2025 COT - RSME - Mechanical Final Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.
02/19/2025 COT - RSPL - Plumbing Final Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.
02/19/2025 ENGR Engineering Final Passed
02/19/2025 RSBU - Building Final Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.
02/19/2025 RSBU - Building Progress Passed Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and fully functional. Fire alarms are installed and operational. GFCI & AFCI breakers are installed in panel and where required by code for kitchen, bathroom, laundry room, and exterior outlets. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SI CERT LOT 14 2462 S CLOVIS_V1.PDF DOCUMENTS VIEW
SITE PLAN LOT 14 2462 S CLOVIS_V1.PDF DOCUMENTS VIEW