Start Date Submittal Complete Date Status  
04/28/2023 RESIDENTIAL NEW DWELLING v.1 05/10/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0123-00207
Permit Status: Issued
Permit Description: SFR LENNLE4005 T22-M0049
Total Outstanding Activity Conditions - 6
Date Name
05/10/2023 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
05/10/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/10/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
05/10/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
07/18/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/18/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0123-00207
Permit Description: SFR LENNLE4005 T22-M0049
Total Completed Inspections - 19
Date Description Inspector Results Comments
05/25/2023 COT - RSPL - Rough Soil Passed
05/25/2023 COT - RSPL - Sewer Passed
05/26/2023 COT - RSPL - Yard Water Line Passed
06/02/2023 COT - RSBU - Preslab Passed
06/02/2023 COT - RSEL - Grounding/Bonding Passed
06/08/2023 RSBU - Building Progress Passed Setbacks.
06/28/2023 COT - RSBU - Exterior Clips/Sheathing Passed Missing anchor bolts on exterior foundation will check for them at intermediate
06/28/2023 COT - RSBU - Roof Nailing Passed
09/12/2023 COT - RSPL - Gas Pressure Test Passed
09/13/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
09/20/2023 BULD - Electrical Clearance Passed
09/20/2023 COT - RSBU - Interior Shear Bracing Passed
12/12/2023 COT - BULD - SWG Clearance Passed
12/20/2023 RSBU - Building Final Passed
12/20/2023 COT - RSEL - Electrical Final Passed
12/20/2023 COT - RSEL - Outdoor Lighting Passed
12/20/2023 COT - RSME - Mechanical Final Passed
12/20/2023 COT - RSPL - Gas Final Passed
12/20/2023 COT - RSPL - Plumbing Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LE2-5, 63_4005 SIC-2023-04-20_V1.PDF DOCUMENTS VIEW
LE2 63 4005 CL9_V1.PDF DOCUMENTS VIEW
LE2-5, 63_4005 MODEL MASTER_V1.PDF DOCUMENTS VIEW