Permit Reviews

Permit Number - TC-MDP-0123-00181
Permit Status: Complete
Permit Description: SFR F50E22 T22-M0029
Start Date Submittal Complete Date Status  
09/05/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/05/2023 REQUIRES RESUBMIT Review Details
01/10/2023 RESIDENTIAL NEW DWELLING v.1 01/18/2023 APPROVED Review Details
09/06/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/07/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0123-00181
Permit Status: Complete
Permit Description: SFR F50E22 T22-M0029
Total Outstanding Activity Conditions - 1
Date Name
01/18/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0123-00181
Permit Status: Complete
Permit Description: SFR F50E22 T22-M0029
Date Description Comments
09/06/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
09/06/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/18/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/06/2023 Post-Tension Inspection Report is required.
09/06/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
09/06/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00181
Permite Description: SFR F50E22 T22-M0029
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
05/24/2023 RSME - Mechanical Progress N/A Not Ready
05/24/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required (with fee) 5/24/23: gas line to on test, nail plate line set, seal penetrations in top plate, seal penetrations in lath, retype exhaust fan in laundry, install B-vent flange correctly, fire block horizontal chase mid point, C/O missing at master bath vanity, secure romex within 12" of box, reseal all gaps in weep screed.
INSPECTION STOPPED, MORE ITEMS MAY BE ADDED.
05/24/2023 COT - RSPL - Gas Pressure Test N/A Re-inspection required 5/24/23: gas line to on test, nail plate line set, seal penetrations in top plate, seal penetrations in lath, retype exhaust fan in laundry, install B-vent flange correctly, fire block horizontal chase mid point, C/O missing at master bath vanity, secure romex within 12" of box, reseal all gaps in weep screed.
INSPECTION STOPPED, MORE ITEMS MAY BE ADDED.
02/22/2023 COT - RSEL - Grounding/Bonding N/A Canceled canceled per contractor

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00181
Permit Description: SFR F50E22 T22-M0029
Total Completed Inspections - 25
Date Description Inspector Results Comments
02/14/2023 COT - RSPL - Rough Soil Passed
02/14/2023 COT - RSPL - Sewer Passed
02/14/2023 COT - RSPL - Yard Water Line Passed
02/23/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
02/23/2023 COT - RSBU - Preslab Passed
04/19/2023 COT - RSBU - Roof Nailing Passed
04/21/2023 COT - RSBU - Exterior Clips/Sheathing Passed
05/30/2023 RSME - Mechanical Progress Passed
05/30/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
05/30/2023 COT - RSPL - Gas Pressure Test Passed
06/30/2023 BULD - Electrical Clearance Passed
07/06/2023 COT - RSBU - Interior Shear Bracing Passed
08/29/2023 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 8/29/2023
09/11/2023 COT - FCON - Fire - Final Passed
09/11/2023 COT - FCON - Sprinkler - Final Passed
09/11/2023 COT - RSME - Mechanical Final Passed
09/11/2023 COT - RSEL - Outdoor Lighting Passed
09/11/2023 COT - RSEL - Grounding/Bonding Passed
09/11/2023 COT - RSEL - Electrical Underground Passed
09/11/2023 RSBU - Building Progress Passed
09/11/2023 RSPL - Plumbing Progress Passed
09/11/2023 COT - RSPL - Gas Final Passed
09/11/2023 COT - RSPL - Plumbing Final Passed
09/12/2023 COT - RSEL - Electrical Final Passed
09/12/2023 RSBU - Building Final Passed

Documents

File Name Document Type  
152455 - SAGUARO TRAILS LOT 3230 - PT REPORT-2023-09-05_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2023-01-09_V1.PDF DOCUMENTS VIEW
CONS-1_SITE PLAN_V1.PDF DOCUMENTS VIEW