Permit: TC-FBB-1024-00191
Permit Details
Apply Date:
10/25/2024
Applicant:
Brianna Quiroz
Description:
I'm applying for a structures permit so we can get temporary power at our construction trailer for our project manager. Please tie this to our approved temporary USE permit (TZ-PMT-0924-00066)
Permit Reviews
Permit Number - TC-FBB-1024-00191
Permit Status: Inspections complete
Permit Description: I'm applying for a structures permit so we can get temporary power at our construction trailer for our project manager. Please tie this to our approved temporary USE permit (TZ-PMT-0924-00066)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/29/2024 | FACTORY BUILT BUILDINGS v.1 | 11/21/2024 | APPROVED |
Conditions
Permit Number - TC-FBB-1024-00191
Permit Status: Inspections complete
Permit Description: I'm applying for a structures permit so we can get temporary power at our construction trailer for our project manager. Please tie this to our approved temporary USE permit (TZ-PMT-0924-00066)
Date | Description | Comments |
---|---|---|
10/29/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-FBB-1024-00191
Permit Description: I'm applying for a structures permit so we can get temporary power at our construction trailer for our project manager. Please tie this to our approved temporary USE permit (TZ-PMT-0924-00066)
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/09/2024 | BULD - Electrical Clearance | Passed | 12-9-24, approved for power. ECO clearance issued to TEP. | |
12/09/2024 | COT - RSEL - Grounding/Bonding | Passed | 12-9-24, grounding/bonding approved. | |
12/09/2024 | COT - RSEL - Electrical Final | Passed | 12-9-24, grounding/bonding approved together with electrical final. | |
12/09/2024 | RSBU - Building Final | Passed | 12-9-24, building final, grounding/bonding together with electrical final approved. |