Permit Details

Status:
Inspections Complete
Type:
Factory Built Buildings
Address:
9101 E 22ND ST
Address NEW:
9101 E 22ND ST
Apply Date:
09/11/2024
Applicant:
Alan Harman
Description:
New Twice the Ice Structure - State approved plans

Permit Reviews

Permit Number - TC-FBB-0924-00161
Permit Status: Inspections complete
Permit Description: New Twice the Ice Structure - State approved plans
Start Date Submittal Complete Date Status  
01/22/2025 RESTAMP - COMMERCIAL v.1 01/23/2025 APPROVED Review Details
09/23/2024 PERMANENT MODULAR v.1 10/29/2024 REQUIRES RESUBMIT Review Details
01/13/2025 PERMANENT MODULAR v.2 01/22/2025 APPROVED Review Details
04/08/2025 PERMANENT MODULAR REVISION v.1 05/06/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-FBB-0924-00161
Permit Status: Inspections complete
Permit Description: New Twice the Ice Structure - State approved plans
Date Description Comments
09/23/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-FBB-0924-00161
Permite Description: New Twice the Ice Structure - State approved plans
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
04/02/2025 COT - LCPL - Sewer N/A Partial Pass Under-slab.
04/17/2025 COT - LCEL - Electrical Underground N/A Not Applicable
04/02/2025 COT - LCPL - Yard Water Line N/A Partial Pass Under-slab
10/16/2026 COT - FCON - Fire - Final N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-FBB-0924-00161
Permit Description: New Twice the Ice Structure - State approved plans
Total Completed Inspections - 14
Date Description Inspector Results Comments
04/04/2025 COT - LCBU - Preslab Passed
04/07/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
04/07/2025 COT - LCBU - Stem Wall/Retaining Wall Passed
04/14/2025 COT - LCPL - Sewer Passed
04/21/2025 COT - LCPL - Yard Water Line Passed
04/22/2025 COT - LCEL - Grounding/Bonding Passed
04/22/2025 BULD - Electrical Clearance Passed ECO
04/28/2025 COT - LCPL - Plumbing Final Passed
04/28/2025 COT - HCBU - Preslab Passed
04/28/2025 COT - LCEL - Electrical Final Passed
10/16/2026 COT - LCBU - Building Final Passed passed
10/16/2026 COT - LCME - Mechanical Final Passed passed
10/16/2026 TRSP - ROW - Notice of Completion Passed
10/16/2026 ENGR Engineering Final Passed