Permit: TC-COM-1225-02294
Permit Details
Apply Date:
12/19/2025
Applicant:
Kelly Rehm
Description:
The El Guero Canelo 12th Ave PV system will consist of 195 500W modules & 3 grid-tied inverters, mounted on 2 new steel parking canopies in the existing parking lots. The system will supply power through an existing TEP service.
Permit Reviews
Permit Number - TC-COM-1225-02294
Permit Status: Complete
Permit Description: The El Guero Canelo 12th Ave PV system will consist of 195 500W modules & 3 grid-tied inverters, mounted on 2 new steel parking canopies in the existing parking lots. The system will supply power through an existing TEP service.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/26/2026 | REQUIRES RESUBMIT |
| 02/10/2026 | COMMERCIAL REVIEW - FULL v.3 | 02/25/2026 | APPROVED |
| 05/07/2026 | SPECIAL INSPECTION REVIEW v.1 | N/A | APPROVED |
| 12/19/2025 | COMMERCIAL REVIEW - FULL v.1 | 01/14/2026 | REQUIRES RESUBMIT |
| 01/22/2026 | COMMERCIAL REVIEW - FULL v.2 | 01/22/2026 | REQUIRES RESUBMIT |
| 03/26/2026 | SPECIAL INSPECTION REVIEW v.2 | 04/01/2026 | APPROVED |
Conditions
Permit Number - TC-COM-1225-02294
Permit Status: Complete
Permit Description: The El Guero Canelo 12th Ave PV system will consist of 195 500W modules & 3 grid-tied inverters, mounted on 2 new steel parking canopies in the existing parking lots. The system will supply power through an existing TEP service.
| Date | Description | Comments |
|---|---|---|
| 01/12/2026 | SPECIAL INSPECTION OF COLD-FORMED STEEL FRAMING IS REQUIRED. | |
| 12/19/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 01/12/2026 | SPECIAL INSPECTION OF FABRICATORS IS REQUIRED | |
| 01/12/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 01/12/2026 | SPECIAL INSPECTION OF STRUCTURAL STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1225-02294
Permite Description: The El Guero Canelo 12th Ave PV system will consist of 195 500W modules & 3 grid-tied inverters, mounted on 2 new steel parking canopies in the existing parking lots. The system will supply power through an existing TEP service.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/10/2026 | COT - CSOL - Outdoor Lighting Solar Project | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1225-02294
Permit Description: The El Guero Canelo 12th Ave PV system will consist of 195 500W modules & 3 grid-tied inverters, mounted on 2 new steel parking canopies in the existing parking lots. The system will supply power through an existing TEP service.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2026 | PDSD Building Division Pre-Construction Meeting | Passed | ||
| 03/04/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 3-4-26: excavation/reinforcement on 9 pier footings verified per detail 101 and pier excavation schedule. Okay for concrete placement at progress areas. | |
| 03/24/2026 | COT - CSOL - Electrical Underground Solar Project | Passed | 03/24/2026 Verified underground (3) 1.25" and (2) 1" schedule 40 conduit run of approximately 50'. Okay to backfill with shading materials. |
|
| 04/10/2026 | BULD - Electrical Clearance | Passed | 4/10/2026 clearance to TEP DGC. | |
| 04/10/2026 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 04/10/2026 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 04/10/2026 | COT - LCBU - Building Final | Passed | ||
| 04/10/2026 | COT - LCBU - Framing | Passed | Approved per third party reports. 4/10/2026 | |
| 04/10/2026 | ENGR Engineering Final | Passed | ||
| 04/10/2026 | TRSP - ROW - Final/Close-Out | Passed |