Permit: TC-COM-1225-02290
Permit Details
Apply Date:
12/18/2025
Applicant:
Description:
New shade structure to cover the east side of the playground area.
Permit Reviews
Permit Number - TC-COM-1225-02290
Permit Status: Inspections
Permit Description: New shade structure to cover the east side of the playground area.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/22/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 01/02/2026 | REQUIRES RESUBMIT |
| 01/02/2026 | COMMERCIAL REVIEW - LIMITED v.2 | 01/02/2026 | APPROVED |
Conditions
Permit Number - TC-COM-1225-02290
Permit Status: Inspections
Permit Description: New shade structure to cover the east side of the playground area.
| Date | Description | Comments |
|---|---|---|
| 12/22/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/22/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-1225-02290
Permite Description: New shade structure to cover the east side of the playground area.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2026 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 2-24-25: excavation for a total of 4 column footers verified per S6.0 details 1, 2, 3,4. Okay for concrete placement. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-1225-02290
Permit Description: New shade structure to cover the east side of the playground area.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2026 | COT - LCBU - Framing | Passed | 3.26.26 Approved per plan |
|
| 03/27/2026 | ENGR Engineering Final | Passed | ||
| 03/31/2026 | COT - LCBU - Building Final | Passed | 3-31-26: building final approved. | |
| 04/01/2026 | TRSP - ROW - Final/Close-Out | Passed |