Permit: TC-COM-1222-00373
Permit Details
Apply Date:
12/28/2022
Applicant:
Samuel Lopez
Description:
Commercial Office Tenant Improvement
Permit Reviews
Permit Number - TC-COM-1222-00373
Permit Status: Complete
Permit Description: Commercial Office Tenant Improvement
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/16/2023 | RESTAMP - COMMERCIAL v.1 | 06/20/2023 | APPROVED |
01/06/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/30/2023 | REQUIRES RESUBMIT |
05/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/30/2023 | REQUIRES RESUBMIT |
06/01/2023 | COMMERCIAL REVIEW - FULL v.3 | 06/16/2023 | APPROVED |
01/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/05/2024 | APPROVED |
Conditions
Permit Number - TC-COM-1222-00373
Permit Status: Complete
Permit Description: Commercial Office Tenant Improvement
Date | Description | Comments |
---|---|---|
06/16/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
06/16/2023 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
06/16/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1222-00373
Permite Description: Commercial Office Tenant Improvement
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/29/2023 | COT - HCME - Mechanical Intermediate | N/A | Not Applicable | 6-29-23: N/A |
06/29/2023 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
06/29/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 6-29-23: Level Five, Phase One. |
06/29/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Re-inspection required | 6-29-23: Remove tile to allow inspection of lay in lights and grills. |
06/29/2023 | COT - HCPL - Plumbing Intermediate | N/A | Not Ready | |
06/29/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Re-inspection required | 6-29-23: Remove tile to allow inspection of lay in lights and grills. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1222-00373
Permit Description: Commercial Office Tenant Improvement
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/02/2023 | COT - HCBU - Building Above Ceiling | Passed | 10/2/23: cancel inspection per Sam. | |
10/02/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 10/2/23: cancel inspection per Sam. PASSED 12/07 |
|
10/02/2023 | BULD - Electrical Clearance | Passed | PASSED10/2/23: cancel inspection per Sam. | |
10/02/2023 | COT - BULD - SWG Clearance | Passed | 10/2/23: cancel inspection per Sam. | |
11/29/2023 | COT - FCON - Fire - Final | Passed | ||
12/01/2023 | ENGR Engineering Final | Passed | ||
11/29/2023 | COT - FCON - Sprinkler - Final | Passed | ||
11/29/2023 | COT - FCON - Alarm - Final | Passed | ||
11/30/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
12/07/2023 | COT - HCME - Mechanical Final | Passed | ||
12/07/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
12/07/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
12/07/2023 | COT - LCBU - Preslab | Passed | ||
12/07/2023 | COT - HCBU - Building Final | Passed | ||
12/07/2023 | COT - HCBU - Framing | Passed | ||
12/07/2023 | COT - HCPL - Plumbing Final | Passed | ||
12/07/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
12/07/2023 | COT - HCEL - Electrical Final | Passed | ||
12/07/2023 | COT - HCME - Mechanical Above Ceiling | Passed |