Permit Details

Status:
Complete
Type:
Commercial Building
Address:
1775 W AJO WY
Apply Date:
12/07/2022
Applicant:
Description:
Tenant improvement and facade renovation to existing shopping center building

Permit Reviews

Permit Number - TC-COM-1222-00252
Permit Status: Complete
Permit Description: Tenant improvement and facade renovation to existing shopping center building
Start Date Submittal Complete Date Status  
05/08/2023 COMMERCIAL REVIEW - FULL v.4 05/19/2023 APPROVED Review Details
11/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/28/2023 APPROVED Review Details
05/19/2023 RESTAMP - COMMERCIAL v.1 05/19/2023 APPROVED Review Details
12/22/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/23/2023 APPROVED Review Details
12/19/2022 COMMERCIAL REVIEW - FULL v.1 01/23/2023 REQUIRES RESUBMIT Review Details
04/11/2023 COMMERCIAL REVIEW - FULL v.3 05/01/2023 REQUIRES RESUBMIT Review Details
01/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/22/2024 APPROVED Review Details
03/07/2023 COMMERCIAL REVIEW - FULL v.2 03/30/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1222-00252
Permit Status: Complete
Permit Description: Tenant improvement and facade renovation to existing shopping center building
Date Description Comments
12/22/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1222-00252
Permite Description: Tenant improvement and facade renovation to existing shopping center building
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
08/03/2023 COT - HCEL - Grounding/Bonding N/A Re-inspection required 8-3-23: Extend existing Ufer to both services.
06/28/2023 COT - HCPL - Plumbing Intermediate N/A Canceled
10/17/2023 COT - HCME - Mechanical Underground N/A Not Applicable
09/11/2023 COT - HCEL - Electrical Progress N/A Partial Pass North porch. and Cafe Janitors closet.
09/05/2023 COT - HCME - Mechanical Above Ceiling N/A Partial Pass 9/5/23: mechanical above ceiling in cafe ok to proceed
08/01/2023 COT - HCPL - Plumbing Above Ceiling N/A Not Ready
12/05/2023 COT - HCPL - Backwater Valve N/A Not Applicable
08/01/2023 COT - HCBU - Framing N/A Partial Pass Walls for Theater, storage, restrooms, catering, and laundry.
12/05/2023 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable
12/07/2023 COT - HCME - Mechanical Final N/A Partial Pass 12/7/23: mechanical final passed on building D.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1222-00252
Permit Description: Tenant improvement and facade renovation to existing shopping center building
Total Completed Inspections - 32
Date Description Inspector Results Comments
06/28/2023 COT - HCEL - Electrical Intermediate Passed 6-28-23: East of sanctuary.
08/01/2023 COT - HCPL - Gas Pressure Test Passed
08/04/2023 COT - HCEL - Grounding/Bonding Passed
09/01/2023 COT - HCPL - Plumbing Intermediate Passed
09/28/2023 COT - LCPL - Yard Water Line Passed 9/28/23: main water line connection made. Passed
10/17/2023 COT - HCBU - Exterior Clips/Sheathing Passed
10/17/2023 COT - HCEL - Electrical Underground Passed
10/19/2023 BULD - Electrical Clearance Passed 7~meter ok for clearance INCR
10/31/2023 COT - HCBU - Building Above Ceiling Passed
10/31/2023 COT - HCEL - Electrical Progress Passed
10/31/2023 COT - HCME - Mechanical Above Ceiling Passed
10/31/2023 COT - HCPL - Plumbing Above Ceiling Passed
10/31/2023 COT - HCPL - Plumbing Progress Passed
11/15/2023 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 11/15/2023
12/05/2023 TRSP - ROW - Final/Close-Out Passed
12/05/2023 COT - HCME - Mechanical Intermediate Passed
12/05/2023 COT - HCPL - Rough Soil Passed
12/05/2023 COT - HCBU - Preslab Passed
12/05/2023 COT - HCBU - Framing Passed
12/05/2023 COT - HCEL - Electrical Above Ceiling Passed
12/05/2023 COT - HCEL - Outdoor Lighting Passed
12/05/2023 COT - HCME - Mechanical Progress Passed
12/05/2023 COT - HCME - Venting Passed
12/07/2023 COT - HCPL - Plumbing Final Passed 11/7/23: passed.
12/12/2023 ENGR Engineering Final Passed
12/13/2023 COT - HCME - Mechanical Final Passed
12/14/2023 COT - FCON - Alarm - Final Passed
12/14/2023 COT - FCON - Fire - Final Passed
12/14/2023 COT - FCON - Sprinkler - Final Passed
12/15/2023 COT - HCBU - Building Final Passed
12/15/2023 COT - HCEL - Electrical Final Passed
01/03/2024 COT - HCBU - CofO Passed 1/3/23: CofO

Documents

File Name Document Type  
CONS-DRAWING SET_V4.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
7608 TC-COM-1222-00252 WESTERN TECH - SPEEDIE SPECIAL_INSPECTION_CERTIFICATES STAMPED TWO-2024-01-18_V1.PDF DOCUMENTS VIEW
7608 TC-COM-1222-00252 - FINAL TAB REPORT 12-20-2023_V1.PDF DOCUMENTS VIEW
7608 WATER CHLORINATION REPORT PERMIT TC-COM-1222-00252 - 23K0618_1 TURNER 11 22 2023 1026-2023-11-27_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-DRAWING SET_V4.PDF DOCUMENTS VIEW