Permit: TC-COM-1125-02149
Permit Details
Apply Date:
11/25/2025
Applicant:
Kelly Rehm
Description:
The YWCA of Southern Arizona PV System will consist of 94 500W modules with 25 grid-tied microinverters supplying power through an existing TEP service. 47.0kW.
Permit Reviews
Permit Number - TC-COM-1125-02149
Permit Status: Complete
Permit Description: The YWCA of Southern Arizona PV System will consist of 94 500W modules with 25 grid-tied microinverters supplying power through an existing TEP service. 47.0kW.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/23/2025 | COMMERCIAL REVIEW - FULL v.2 | 01/07/2026 | APPROVED |
| 12/01/2025 | COMMERCIAL REVIEW - FULL v.1 | 12/23/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1125-02149
Permit Status: Complete
Permit Description: The YWCA of Southern Arizona PV System will consist of 94 500W modules with 25 grid-tied microinverters supplying power through an existing TEP service. 47.0kW.
| Date | Description | Comments |
|---|---|---|
| 12/01/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1125-02149
Permit Description: The YWCA of Southern Arizona PV System will consist of 94 500W modules with 25 grid-tied microinverters supplying power through an existing TEP service. 47.0kW.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/01/2026 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 03/03/2026 | COT - CSOL - Electrical Final Solar Project | Passed | 3.3.26 Approved, PV system installed per plans |
|
| 03/03/2026 | ENGR Engineering Final | Passed | Work is complete, site is safe. | |
| 03/03/2026 | COT - LCBU - Building Final | Passed | 3.3.26 Approved, PV system installed per plans |
|
| 03/03/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/16/2026 | BULD - Electrical Clearance | Passed | 3.16.26 Approved for DGC clearance to TEP |