Permit Details

Status:
Complete
Type:
Commercial Building
Address:
9650 E 22ND ST
Address NEW:
9650 E 22ND ST
Apply Date:
11/15/2024
Applicant:
Cam Hemmen
Description:
THIS IS AN EXISTING RETAIL ESTABLISHMENT BEING REMODELED FOR A NEW TENANT WITH UPDATED EQUIPMENT, FIXTURES, AND FINISHES. EXTERIOR WORK INCLUDES ADDING A NEW DOUBLE DOOR AT THE BACK OF TENANT SPACE FOR MERCHANDISE LOADING AND DELIVERY. FIRE PROTECTIONS/SPRINKLER UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. FIRE ALARM UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. NEW SIGNAGE TO BE UNDER SEPARATE PERMIT.

Permit Reviews

Permit Number - TC-COM-1124-02208
Permit Status: Complete
Permit Description: THIS IS AN EXISTING RETAIL ESTABLISHMENT BEING REMODELED FOR A NEW TENANT WITH UPDATED EQUIPMENT, FIXTURES, AND FINISHES. EXTERIOR WORK INCLUDES ADDING A NEW DOUBLE DOOR AT THE BACK OF TENANT SPACE FOR MERCHANDISE LOADING AND DELIVERY. FIRE PROTECTIONS/SPRINKLER UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. FIRE ALARM UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. NEW SIGNAGE TO BE UNDER SEPARATE PERMIT.
Start Date Submittal Complete Date Status  
04/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/10/2025 APPROVED Review Details
01/13/2025 COMMERCIAL REVIEW - FULL v.2 01/21/2025 APPROVED Review Details
11/15/2024 COMMERCIAL REVIEW - FULL v.1 12/10/2024 REQUIRES RESUBMIT Review Details
04/29/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/01/2025 APPROVED Review Details
01/21/2025 RESTAMP - COMMERCIAL v.1 01/23/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-1124-02208
Permit Status: Complete
Permit Description: THIS IS AN EXISTING RETAIL ESTABLISHMENT BEING REMODELED FOR A NEW TENANT WITH UPDATED EQUIPMENT, FIXTURES, AND FINISHES. EXTERIOR WORK INCLUDES ADDING A NEW DOUBLE DOOR AT THE BACK OF TENANT SPACE FOR MERCHANDISE LOADING AND DELIVERY. FIRE PROTECTIONS/SPRINKLER UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. FIRE ALARM UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. NEW SIGNAGE TO BE UNDER SEPARATE PERMIT.
Date Description Comments
01/15/2025 AIR BALANCING REPORT IS REQUIRED.
01/15/2025 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
01/15/2025 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/15/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
11/15/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
01/15/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
11/15/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
01/15/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
01/15/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02208
Permite Description: THIS IS AN EXISTING RETAIL ESTABLISHMENT BEING REMODELED FOR A NEW TENANT WITH UPDATED EQUIPMENT, FIXTURES, AND FINISHES. EXTERIOR WORK INCLUDES ADDING A NEW DOUBLE DOOR AT THE BACK OF TENANT SPACE FOR MERCHANDISE LOADING AND DELIVERY. FIRE PROTECTIONS/SPRINKLER UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. FIRE ALARM UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. NEW SIGNAGE TO BE UNDER SEPARATE PERMIT.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
03/26/2025 BULD - Electrical Clearance N/A Not Applicable
03/26/2025 COT - BULD - SWG Clearance N/A Not Applicable
02/13/2025 COT - HCBU - Building Progress N/A Partial Pass 2-13-25, partial pass on above ceiling grid for IT room, storage areas. Grid not quite complete but contractor has another inspection for same next week.
02/18/2025 COT - HCME - Mechanical Progress N/A Partial Pass 2-18-25, all duct work for IT room together with storage area installed. Okay to continue with construction.
01/28/2025 COT - HCPL - Plumbing Progress N/A Partial Pass 1-28-25, verified plumbing under pressure. Okay to continue with construction remodel.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02208
Permit Description: THIS IS AN EXISTING RETAIL ESTABLISHMENT BEING REMODELED FOR A NEW TENANT WITH UPDATED EQUIPMENT, FIXTURES, AND FINISHES. EXTERIOR WORK INCLUDES ADDING A NEW DOUBLE DOOR AT THE BACK OF TENANT SPACE FOR MERCHANDISE LOADING AND DELIVERY. FIRE PROTECTIONS/SPRINKLER UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. FIRE ALARM UPDATES TO BE BY CONTRACTOR UNDER A SEPARATE PERMIT. NEW SIGNAGE TO BE UNDER SEPARATE PERMIT.
Total Completed Inspections - 18
Date Description Inspector Results Comments
02/10/2025 COT - HCBU - Framing Passed Rough framing is complete. Okay to one-side with drywall floor to bottom of roof trusses.
02/12/2025 COT - HCME - Mechanical Above Ceiling Passed 2/12/25: Mechanical above ceiling in office and bathrooms is complete. Okay to install drywall hard lid ceiling in bathrooms and grid ceiling in office space.
03/25/2025 ENGR Engineering Final Passed CO Ready, dumpster will be taken over by tenant.
03/25/2025 COT - FCON - Fire - Final Passed
03/25/2025 COT - HCEL - Electrical Final Passed
03/26/2025 COT - HCBU - Building Above Ceiling Passed
03/26/2025 COT - HCBU - Building Progress Passed
03/26/2025 COT - HCBU - Preslab Passed
03/26/2025 COT - HCEL - Electrical Above Ceiling Passed
03/26/2025 COT - HCEL - Electrical Progress Passed
03/26/2025 COT - HCME - Mechanical Progress Passed
03/26/2025 COT - HCPL - Plumbing Above Ceiling Passed
03/26/2025 COT - HCPL - Plumbing Progress Passed
04/22/2025 COT - HCBU - Building Final Passed
04/22/2025 COT - HCME - Mechanical Final Passed
04/22/2025 COT - HCPL - Plumbing Final Passed
04/23/2025 COT - HCBU - CofO Passed
04/28/2025 TRSP - ROW - Final/Close-Out Passed Work performed on private property

Documents

File Name Document Type  
AIR BALANCE REPORT_V1.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
TC-COM-1124-02208_DAISO STORE REMODEL_63251003 - SIGNED-2025-04-29_V1.PDF DOCUMENTS VIEW
MCMANUS CON. - DAISO (PHASE 2) LAB RESULTS-2025-04-02_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-TC-COM-1124-02208 - DAISO TUCSON BLDG TI PLANS 01092025_V2.PDF DOCUMENTS VIEW
TC-COM-1124-02208 - DAISO TUCSON BLDG TI CALCS 01092025_V1.PDF DOCUMENTS VIEW
TC-COM-1124-02208 - DAISO TUCSON BLDG TI SI FORM 01092025-2025-01-09_V1.PDF DOCUMENTS VIEW