Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
11/10/2023
Applicant:
Eric Lush
Description:
New Bldg 3 Pre-engineered Metal Building for Warehouse

Permit Reviews

Permit Number - TC-COM-1123-02635
Permit Status: Complete
Permit Description: New Bldg 3 Pre-engineered Metal Building for Warehouse
Start Date Submittal Complete Date Status  
02/01/2024 RESTAMP - COMMERCIAL v.1 02/01/2024 APPROVED Review Details
01/31/2024 RESTAMP - COMMERCIAL v.1 01/31/2024 APPROVED Review Details
01/31/2024 COMMERCIAL REVIEW - FULL v.2 02/01/2024 APPROVED Review Details
09/27/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/03/2024 APPROVED Review Details
11/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/18/2024 REQUIRES RESUBMIT Review Details
11/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/19/2024 APPROVED Review Details
11/16/2023 COMMERCIAL REVIEW - FULL v.1 01/25/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1123-02635
Permit Status: Complete
Permit Description: New Bldg 3 Pre-engineered Metal Building for Warehouse
Date Description Comments
01/25/2024 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
01/25/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/25/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
11/16/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
01/25/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
01/25/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
01/25/2024 Post-Installed Anchor Inspection Report is required.
02/05/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
01/25/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
11/19/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
01/25/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1123-02635
Permite Description: New Bldg 3 Pre-engineered Metal Building for Warehouse
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/03/2024 COT - HCPL - Sewer N/A Partial Pass From building to easement.
05/09/2024 COT - HCEL - Grounding/Bonding N/A Partial Pass

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1123-02635
Permit Description: New Bldg 3 Pre-engineered Metal Building for Warehouse
Total Completed Inspections - 28
Date Description Inspector Results Comments
04/22/2024 COT - HCPL - Rough Soil Passed Underground plumbing is complete and under a pressure test with no leaks. Okay to shade pipes and backfill trenches.
04/29/2024 COT - HCPL - Yard Water Line Passed Ok to backfill
05/09/2024 COT - HCBU - Preslab Passed
05/29/2024 COT - HCPL - Sewer Passed
07/23/2024 COT - HCEL - Electrical Underground Passed
08/07/2024 COT - HCBU - Exterior Clips/Sheathing Passed
08/07/2024 COT - HCBU - Roof Nailing Passed
08/23/2024 COT - HCEL - Electrical Intermediate Passed
08/23/2024 COT - HCEL - Grounding/Bonding Passed
08/23/2024 COT - HCBU - Framing Passed
08/23/2024 COT - HCME - Mechanical Above Ceiling Passed
08/23/2024 COT - HCPL - Plumbing Above Ceiling Passed
08/26/2024 COT - HCPL - Plumbing Intermediate Passed
09/20/2024 BULD - Electrical Clearance Passed
10/07/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
10/16/2024 COT - HCEL - Electrical Above Ceiling Passed
10/16/2024 COT - HCME - Mechanical Intermediate Passed
10/16/2024 COT - HCEL - Outdoor Lighting Passed
10/16/2024 COT - HCBU - Building Above Ceiling Passed
11/05/2024 COT - FCON - Sprinkler - Final Passed
11/05/2024 COT - FCON - Alarm - Final Passed
11/05/2024 COT - HCEL - Electrical Final Passed
11/05/2024 TRSP - ROW - Final/Close-Out Passed
11/08/2024 COT - HCPL - Plumbing Final Passed
11/15/2024 ENGR Engineering Final Passed
11/15/2024 COT - HCME - Mechanical Final Passed
11/25/2024 COT - FCON - Fire - Final Passed
11/26/2024 COT - HCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
63231192.AGM CONTAINER CONTROLS NEW WAREHOUSE BLDG - SIGNED UN LOCKED-2024-11-18_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-CONS-STANTEC_APPROVED_PLANS_V1-5_V2.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_ENERGY_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_PEMB_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_GEOTECH_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_PEMB_LETTER_OF_CERT_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_SPECS_LIGHTING_V1.PDF DOCUMENTS VIEW
STANTEC_SPEC_INSP_CERT-2024-01-24_V1.PDF DOCUMENTS VIEW
CONS-CONS-STANTEC_APPROVED_PLANS_V1-5_V2.PDF DOCUMENTS VIEW