Permit: TC-COM-1123-02599
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5055 E BROADWAY BL
Address NEW:
5055 E BROADWAY BL
Apply Date:
11/06/2023
Applicant:
Brandy Burke
Description:
New elevator and siting area 84 sq ft for elevator 456 total sitting area and elevator
Permit Reviews
Permit Number - TC-COM-1123-02599
Permit Status: Complete
Permit Description: New elevator and siting area
84 sq ft for elevator
456 total sitting area and elevator
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/27/2025 | APPROVED |
| 03/19/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/26/2025 | REQUIRES RESUBMIT |
| 03/19/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/24/2025 | APPROVED |
| 12/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/09/2024 | APPROVED |
| 01/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/05/2024 | APPROVED |
| 01/05/2024 | RESTAMP - COMMERCIAL v.1 | 01/09/2024 | APPROVED |
| 11/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/04/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1123-02599
Permit Status: Complete
Permit Description: New elevator and siting area
84 sq ft for elevator
456 total sitting area and elevator
| Date | Description | Comments |
|---|---|---|
| 01/02/2024 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 12/06/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/27/2025 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 12/06/2024 | SPECIAL INSPECTION FOR EPOXY REINFORCEMENT IS REQUIRED. | |
| 01/02/2024 | Masonry Inspection Report submittal review is required. | |
| 12/06/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL IS REQUIRED. | |
| 12/06/2024 | SPECIAL INSPECTION FOR SOILS IS REQUIRED. | |
| 01/02/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02599
Permite Description: New elevator and siting area
84 sq ft for elevator
456 total sitting area and elevator
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 03/25/2024 | COT - HCEL - Electrical Underground | N/A | Not Applicable | |
| 05/08/2024 | COT - HCBU - Roof Nailing | N/A | Canceled | 5/8/24: Canceled per contractor |
| 05/08/2024 | COT - HCBU - Framing | N/A | Canceled | 5/8/24: Canceled per contractor |
| 04/04/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 4-4-25, not applicable. |
| 04/04/2025 | COT - HCBU - Building Final | N/A | Partial Pass | 4-4-24, pending Development Package & Engineering final. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02599
Permit Description: New elevator and siting area
84 sq ft for elevator
456 total sitting area and elevator
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 04/10/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Rebar reinforcement is placed per plans for elevator pit/wall and garden wall footings. Okay to pour concrete. | |
| 04/10/2024 | COT - HCBU - Preslab | Passed | Rebar reinforcement is placed per plans for elevator pit/wall and garden wall footings. Okay to pour concrete. | |
| 04/10/2024 | COT - HCEL - Electrical Above Ceiling | Passed | Electrical conduits are installed from 2nd floor electrical room to elevator location. All penetration have been sealed with fire proof caulking. Okay to proceed with further work. | |
| 05/02/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
| 05/10/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | Ok to grout progress areas. | |
| 05/10/2024 | COT - HCBU - Roof Nailing | Passed | Ok to dry-in roof system. | |
| 05/16/2024 | COT - HCBU - Framing | Passed | ||
| 06/13/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 06/13/2024 | COT - HCME - Mechanical Final | Passed | ||
| 06/13/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 06/13/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 06/13/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 04/04/2025 | COT - FCON - Fire - Final | Passed | The elevator reports are attached to the permit. | |
| 04/04/2025 | ENGR Engineering Final | Passed | ||
| 04/04/2025 | COT - HCEL - Electrical Final | Passed | 4-4-25, electrical final approved. |