Status:
Complete
Type:
Commercial Building
Address NEW:
1390 W SPEEDWAY BL
Apply Date:
11/07/2022
Applicant:
Cary Broschat
Description:
110kW AC solar shade canopy installation

Permit Reviews

Permit Number - TC-COM-1122-00059
Permit Status: Complete
Permit Description: 110kW AC solar shade canopy installation
Start Date Submittal Complete Date Status  
01/23/2023 COMMERCIAL REVIEW - FULL v.2 02/07/2023 APPROVED Review Details
11/15/2022 COMMERCIAL REVIEW - FULL v.1 12/15/2022 REQUIRES RESUBMIT Review Details
05/05/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/08/2023 APPROVED Review Details

Conditions

Permit Number - TC-COM-1122-00059
Permit Status: Complete
Permit Description: 110kW AC solar shade canopy installation
Date Description Comments
12/15/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
12/15/2022 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1122-00059
Permite Description: 110kW AC solar shade canopy installation
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
04/07/2023 COT - LCEL - Electrical Underground N/A Partial Pass 3/20/23 - Partial for grounding by metal column embedment per plan

3/24/23 - Partial for conduit
stub up at column of the equipment location, okay for concrete

3/29/23 - Partial for continuation of conduits from Panel 1 to light pedestal at Meter 2 location, okay backfill progress areas

4/4/23- Backfill ok for Meter 1 to Canopy 1 and Meter 2 to Canopy 2
04/20/2023 COT - LCBU - Building Progress N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1122-00059
Permit Description: 110kW AC solar shade canopy installation
Total Completed Inspections - 10
Date Description Inspector Results Comments
03/20/2023 COT - LCEL - Grounding/Bonding Passed Approved, grounding by metal column embedment per plan
03/21/2023 COT - LCBU - Excavation/Rebar/Zoning Passed
03/21/2023 COT - LCBU - Preslab Passed
04/10/2023 COT - LCEL - Electrical Underground Passed
04/20/2023 COT - LCBU - Framing Passed Approved per special inspection, east canopy
04/20/2023 COT - LCEL - Electrical Intermediate Passed
04/20/2023 COT - LCEL - Outdoor Lighting Passed
07/09/2023 COT - LCBU - Building Final Passed
07/09/2023 BULD - Electrical Clearance Passed 7/9/2023 verbal clearance for TEP DGC/DGL meter #1 ERP (El Rio Park) from transformer #4.
07/09/2023 COT - LCEL - Electrical Final Passed