Permit: TC-COM-1122-00019
Permit Details
Apply Date:
11/01/2022
Applicant:
Brandy Burke
Description:
Outdoor stage and meeting area with landscape improvements
Permit Reviews
Permit Number - TC-COM-1122-00019
Permit Status: Complete
Permit Description: Outdoor stage and meeting area with landscape improvements
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/24/2023 | COMMERCIAL REVIEW - FULL v.2 | 02/15/2023 | REQUIRES RESUBMIT |
03/15/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/22/2023 | APPROVED |
11/05/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/21/2022 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00019
Permite Description: Outdoor stage and meeting area with landscape improvements
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2023 | COT - HCPL - Sewer | N/A | Re-inspection required | 7/11/23: no contact person or phone number in notes. This inspection is canceled. |
10/05/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Not Applicable | |
10/05/2023 | COT - HCBU - Masonry Pregrout | N/A | Deferred | 10/5/23: all grout lifts were grouted WITHOUT a city Inspection. A third-party was present at all grout lifts, who reported to the Engineer of Record. |
COT - FCON - Fire - Final | N/A | Not Ready | Wanted to remove sprinklers from permit due to non sprinklered building. | |
10/26/2023 | BULD - Electrical Clearance | N/A | Partial Pass | 10/26/23: Reinforcement per plan on stage ok to pour. (Wanted to call in Preslab) |
01/17/2024 | COT - HCBU - Building Final | N/A | Not Ready | |
09/21/2023 | COT - HCBU - Preslab | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00019
Permit Description: Outdoor stage and meeting area with landscape improvements
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2023 | COT - HCPL - Sewer | Passed | 7/11/23: no contact person or phone number in notes. This inspection is canceled. 7/12/23: new 4" sewer from tie-in to end of line at two-way clean outs approved to cover. 7/18/23: new future sewer from clean-out (approximately 2 feet) OK to cover. |
|
07/18/2023 | COT - HCBU - Building Progress | Passed | ||
07/18/2023 | COT - HCPL - Backwater Valve | Passed | ||
07/25/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
09/12/2023 | COT - HCEL - Electrical Underground | Passed | Approved underground secondary and data conduits from panel location in storage room to the back stage area | |
09/12/2023 | COT - HCPL - Yard Water Line | Passed | Approved 3/4 water line to HB at northeast corner of building, okay to shade | |
10/05/2023 | COT - HCBU - Roof Nailing | Passed | 10/5/23: roof nailing for open area on north side of building | |
10/05/2023 | COT - HCBU - Framing | Passed | 10/5/23: roof framing for open area on north side of building approved. | |
12/19/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
02/06/2024 | COT - FCON - Fire - Final | Passed | ||
02/07/2024 | COT - HCBU - Building Final | Passed | 2/7/24: Shell building and stage are complete. Electrical exterior and interior lights are installed and operational. Sewer line and water main are stubbed up to the interior of shell building. Okay to issue Letter of Completion. | |
03/01/2024 | COT - HCBU - Preslab | Passed | Perimeter slab is poured. Middle section of flooring will be poured by others under a separate permit for the tenant improvements. Okay to issue letter of completion for this permit. | |
03/27/2024 | SITE - Zoning Final | Passed |