Permit: TC-COM-1026-01658
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
1316 E 21ST ST
Address NEW:
1316 E 21ST ST
Apply Date:
10/06/2026
Applicant:
Martha Johnson
Description:
Arrived onsite to inspect existing gas lines found that they have been operating with a undersized system that was installed without permit or inspection being performed checked btu count and got linear footage for system. Needs to be replaced to be up to code standards will get info together and submit estimate for required Work to be performed took pics of units have a total of 140 ft from meter to furthest furnace We will run new gas pipe from meter to 2 crematory pits and 1 suspended heater Has a combined total of 5.2 million btu per hr. count We will supply and install new gas piping to proper size for system Includes new isolation valves at take off and at units Pics of all work performed will be provided Includes permit and inspection of work performed Please note that if any cc plumbing doesn’t meet code additional charge will occur Gas line will be suspended from roof using clevis hangers for support Once work is completed will pump system up to 15 psi to check for leaks Estimate includes any code upgrades pertaining to gas installation only New gas line comes with 2 yr warranty from ram Gas line to be run in 1 1/2 1 1/4 and 1” black steel
Permit Reviews
Permit Number - TC-COM-1026-01658
Permit Status: Needs resubmittal
Permit Description: Arrived onsite to inspect existing gas lines found that they have been operating with a undersized system that was installed without permit or inspection being performed checked btu count and got linear footage for system.
Needs to be replaced to be up to code standards will get info together and submit estimate for required
Work to be performed took pics of units have a total of 140 ft from meter to furthest furnace
We will run new gas pipe from meter to 2 crematory pits and 1 suspended heater
Has a combined total of 5.2 million btu per hr. count
We will supply and install new gas piping to proper size for system
Includes new isolation valves at take off and at units
Pics of all work performed will be provided
Includes permit and inspection of work performed
Please note that if any cc plumbing doesn’t meet code additional charge will occur
Gas line will be suspended from roof using clevis hangers for support
Once work is completed will pump system up to 15 psi to check for leaks
Estimate includes any code upgrades pertaining to gas installation only
New gas line comes with 2 yr warranty from ram
Gas line to be run in 1 1/2 1 1/4 and 1” black steel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/06/2026 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 10/06/2026 | REQUIRES RESUBMIT |