Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-1024-02072
Permit Details
Apply Date:
10/28/2024
Applicant:
Brandy Burke
Description:
T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Permit Reviews
Permit Number - TC-COM-1024-02072
Permit Status: Issued
Permit Description: T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/30/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/25/2024 | REQUIRES RESUBMIT |
12/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/02/2025 | APPROVED |
12/13/2024 | COMMERCIAL REVIEW - FULL v.2 | 12/23/2024 | APPROVED |
12/23/2024 | RESTAMP - COMMERCIAL v.1 | 12/27/2024 | APPROVED |
Conditions
Permit Number - TC-COM-1024-02072
Permit Status: Issued
Permit Description: T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Date | Description | Comments |
---|---|---|
12/13/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-1024-02072
Permite Description: T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
COT - FCON - Sprinkler - Final | N/A | Scheduled | ||
12/31/2024 | COT - HCBU - CofO | N/A | Partial Pass | OK to make application for Temporary Certificate of Occupancy for all areas except for eatery areas. Level 4. |
01/15/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok for Level 3 TCO. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-1024-02072
Permit Description: T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Total Completed Inspections - 15
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/31/2024 | BULD - Electrical Clearance | Passed | No clearance required. | |
12/31/2024 | COT - BULD - SWG Clearance | Passed | No gas clearance required. | |
12/31/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
12/31/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
12/31/2024 | COT - HCEL - Electrical Progress | Passed | ||
12/31/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
12/31/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
12/31/2024 | COT - HCBU - Framing | Passed | ||
12/31/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
12/31/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
12/31/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
12/31/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
12/31/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
01/15/2025 | ENGR Engineering Final | Passed | ||
01/14/2025 | TRSP - ROW - Final/Close-Out | Passed |
Scheduled Inspections
Scheduled Inspections - TC-COM-1024-02072
Status: Issued
Description: T.I. project within existing shell building envelope. New underground and in-wall plumbing and electrical work.
Scheduled Date | Description | Entered By | Entered Date |
---|---|---|---|
12/31/2024 | COT - FCON - Sprinkler - Final | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.