Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-1024-02062
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1601 W SAINT MARYS RD
Address NEW:
1601 W SAINT MARYS RD
Apply Date:
10/27/2024
Applicant:
Ann Laws
Description:
Renovation of existing CT scan room with new CT equipment.
Permit Reviews
Permit Number - TC-COM-1024-02062
Permit Status: Complete
Permit Description: Renovation of existing CT scan room with new CT equipment.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/30/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/25/2024 | REQUIRES RESUBMIT |
| 01/09/2025 | RESTAMP - COMMERCIAL v.1 | 01/13/2025 | APPROVED |
| 01/08/2025 | COMMERCIAL REVIEW - FULL v.3 | 01/09/2025 | APPROVED |
| 12/23/2024 | COMMERCIAL REVIEW - FULL v.2 | 12/23/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-1024-02062
Permit Status: Complete
Permit Description: Renovation of existing CT scan room with new CT equipment.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/09/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 01/09/2025 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 01/09/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 01/09/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-1024-02062
Permit Status: Complete
Permit Description: Renovation of existing CT scan room with new CT equipment.
| Date | Description | Comments |
|---|---|---|
| 01/09/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1024-02062
Permit Description: Renovation of existing CT scan room with new CT equipment.
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2025 | COT - HCPL - Medical Gas/Test | Passed | Medical gas system tested and inspected by second party special inspector. | |
| 09/19/2025 | COT - HCBU - Framing | Passed | Ct room approved. 9/19/2025 | |
| 09/19/2025 | COT - HCPL - Plumbing Progress | Passed | New lines for sink in place and secured. 9/19/2025 | |
| 10/24/2025 | COT - HCBU - Building Progress | Passed | ||
| 10/24/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 10/24/2025 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 10/24/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 10/24/2025 | COT - HCEL - Electrical Progress | Passed | ||
| 11/14/2025 | ENGR Engineering Final | Passed | Site is safe and accessible. | |
| 11/13/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 11/17/2025 | COT - HCEL - Grounding/Bonding | Passed | ||
| 11/17/2025 | COT - HCME - Mechanical Final | Passed | ||
| 11/17/2025 | COT - HCME - Mechanical Progress | Passed | ||
| 11/17/2025 | COT - HCPL - Medical Gas/Final | Passed | ||
| 11/17/2025 | COT - HCPL - Plumbing Final | Passed | ||
| 11/17/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 11/17/2025 | COT - HCBU - Building Final | Passed | ||
| 11/17/2025 | COT - HCEL - Electrical Final | Passed | ||
| 11/17/2025 | BULD - Electrical Clearance | Passed | No clearance required. | |
| 11/17/2025 | COT - BULD - SWG Clearance | Passed | No clearance required. | |
| 11/17/2025 | COT - FCON - Alarm - Final | Passed | ||
| 11/17/2025 | COT - FCON - Fire - Final | Passed | ||
| 11/17/2025 | COT - FCON - Sprinkler - Final | Passed |