Permit: TC-COM-1024-02020
Permit Details
Status:
Inspections Complete
Type:
Commercial Building
Address:
707 E LEE ST UNIT 8
Address NEW:
707 E LEE ST UNIT 8
Apply Date:
10/21/2024
Applicant:
Alexander Lee
Description:
UNIT 8 - THE SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLERS WITH PACKAGE ROOF TOP HEAT PUMPS AND UPGRADING ELECTRIC PANEL
Permit Reviews
Permit Number - TC-COM-1024-02020
Permit Status: Inspections complete
Permit Description: UNIT 8 - THE SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLERS WITH PACKAGE ROOF TOP HEAT PUMPS AND UPGRADING ELECTRIC PANEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/26/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 11/27/2024 | APPROVED |
| 11/25/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/26/2024 | APPROVED |
| 10/23/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 11/07/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1024-02020
Permit Status: Inspections complete
Permit Description: UNIT 8 - THE SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLERS WITH PACKAGE ROOF TOP HEAT PUMPS AND UPGRADING ELECTRIC PANEL
| Date | Description | Comments |
|---|---|---|
| 10/23/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 10/23/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-1024-02020
Permite Description: UNIT 8 - THE SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLERS WITH PACKAGE ROOF TOP HEAT PUMPS AND UPGRADING ELECTRIC PANEL
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2024 | COT - LCBU - Building Final | N/A | Not Ready | |
| 12/11/2024 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 12/11/2024 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 12/27/2024 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | 12-27-24, per contractor, electrical work was made to unit but never inspected prior to being covered up. Contractor must submit a letter to the city for review indicating that work was done per approved plans and meets 2018 IRC requirements. |
| 12/27/2024 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | 12-27-24, per contractor, electrical work was made to unit but never inspected prior to being covered up. Contractor must submit a letter to the city for review indicating that work was done per approved plans and meets 2018 IRC requirements. |
| 12/27/2024 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | 12-27-24, per contractor, duct work was made to unit but never inspected prior to being covered up. Contractor must submit a letter to the city for review indicating that work was done per approved plans and meets 2018 IRC requirements. |
| 12/27/2024 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | 12-27-24, per contractor, duct work was made to unit but never inspected prior to being covered up. Contractor must submit a letter to the city for review indicating that work was done per approved plans and meets 2018 IRC requirements. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-1024-02020
Permit Description: UNIT 8 - THE SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLERS WITH PACKAGE ROOF TOP HEAT PUMPS AND UPGRADING ELECTRIC PANEL
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2024 | BULD - Electrical Clearance | Passed | ||
| 12/11/2024 | COT - FCON - Fire - Final | Passed | air conditioning units only | |
| 12/11/2024 | ENGR Engineering Final | Passed | ||
| 12/11/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 12/11/2024 | COT - LCBU - Roof Nailing | Passed | ||
| 12/17/2024 | COT - BULD - SWG Clearance | Passed | Address should read Unit #4 not #8. Ok to set meter. | |
| 07/02/2025 | COT - LCBU - Building Final | Passed | ||
| 07/02/2025 | COT - LCEL - Electrical Final | Passed | ||
| 07/02/2025 | COT - LCME - Mechanical Final | Passed | ||
| 07/02/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 07/02/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 07/02/2025 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 07/02/2025 | COT - LCME - Mechanical Intermediate | Passed |