Permit: TC-COM-1023-02521
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3719 N CAMPBELL AV
Address NEW:
3719 N CAMPBELL AV
Apply Date:
10/25/2023
Applicant:
Lisa Bowers
Description:
TI: new walls/partitions, replace windows/doors, new acoustical ceiling tile and gypsum board suspended ceilings. No exterior work.
Permit Reviews
Permit Number - TC-COM-1023-02521
Permit Status: Complete
Permit Description: TI: new walls/partitions, replace windows/doors, new acoustical ceiling tile and gypsum board suspended ceilings. No exterior work.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/18/2024 | APPROVED |
| 03/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/26/2024 | APPROVED |
| 01/18/2024 | RESTAMP - COMMERCIAL v.1 | 01/22/2024 | APPROVED |
| 04/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/11/2024 | APPROVED |
| 04/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/17/2024 | APPROVED |
| 04/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/04/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1023-02521
Permit Status: Complete
Permit Description: TI: new walls/partitions, replace windows/doors, new acoustical ceiling tile and gypsum board suspended ceilings. No exterior work.
| Date | Description | Comments |
|---|---|---|
| 01/18/2024 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 10/31/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 04/12/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/12/2024 | Post-Installed Anchor Inspection Report is required. | |
| 01/18/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1023-02521
Permit Description: TI: new walls/partitions, replace windows/doors, new acoustical ceiling tile and gypsum board suspended ceilings. No exterior work.
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/01/2024 | COT - HCBU - Framing | Passed | ||
| 02/01/2024 | COT - HCPL - Rough Soil | Passed | ||
| 02/01/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 02/01/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 02/01/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 02/21/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 03/19/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 03/19/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 03/19/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 03/19/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 03/27/2024 | COT - HCEL - Electrical Final | Passed | ||
| 03/27/2024 | COT - HCME - Mechanical Final | Passed | ||
| 03/27/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 03/27/2024 | COT - FCON - Fire - Final | Passed | ||
| 03/27/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 03/27/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 04/01/2024 | ENGR Engineering Final | Passed | spoke with Adam, PM, portajohn and dumpster removed today. fence blocking access from Campbell to remain per property owner. project is 9n final cleaning touch up. | |
| 03/28/2024 | COT - HCBU - Building Final | Passed |