Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
8205 S CAMINO DE CAFE
Apply Date:
10/23/2023
Applicant:
Chris Guinter
Description:
A-FAMILY - RITA, LOT 9

Permit Reviews

Permit Number - TC-COM-1023-02499
Permit Status: Complete
Permit Description: A-FAMILY - RITA, LOT 9
Start Date Submittal Complete Date Status  
02/13/2024 RESTAMP - COMMERCIAL v.1 02/16/2024 APPROVED Review Details
10/30/2023 COMMERCIAL REVIEW - FULL v.1 11/22/2023 REQUIRES RESUBMIT Review Details
01/30/2025 COMMERCIAL REVIEW - FULL v.1 02/21/2025 APPROVED Review Details
05/11/2026 SPECIAL INSPECTION REVIEW v.2 05/13/2026 APPROVED Review Details
02/06/2024 COMMERCIAL REVIEW - FULL v.2 02/13/2024 APPROVED Review Details
01/13/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/15/2026 APPROVED Review Details
02/26/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/03/2025 APPROVED Review Details
05/07/2026 SPECIAL INSPECTION REVIEW v.1 05/08/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-1023-02499
Permit Status: Complete
Permit Description: A-FAMILY - RITA, LOT 9
Date Description Comments
02/13/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
02/13/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/30/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
05/08/2026 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/13/2024 Metal Building Structure with Calculations Designs must be submitted and approved prior to final.
02/13/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
10/30/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
02/13/2024 Stair Designs must be submitted and approved prior to...
02/13/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02499
Permite Description: A-FAMILY - RITA, LOT 9
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
04/09/2026 COT - BULD - SWG Clearance N/A Not Applicable 4-9-26: not applicable.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02499
Permit Description: A-FAMILY - RITA, LOT 9
Total Completed Inspections - 24
Date Description Inspector Results Comments
02/25/2025 COT - HCPL - Rough Soil Passed 2-25-25, underground plumbing verified as per approved plans. Okay to backfill with shading materials and proceed with construction.
03/14/2025 COT - HCBU - Excavation/Rebar/Zoning Passed 3-14-25, excavation/reinforcement per approved plans. Okay to pour concrete.
03/14/2025 COT - HCBU - Preslab Passed 3-14-25, preslab approved. Okay to pour concrete.
05/30/2025 COT - HCPL - Sewer Passed 5-30-25: verified sewer connection under test and per plans. Okay to backfill approximately 90' of 4" SDR35 plumbing pipe-shading required.
06/05/2025 COT - HCPL - Plumbing Intermediate Passed 6-5-25: plumbing intermediate verified under test and per approved plans. Okay to continue with construction.
06/05/2025 COT - HCPL - Yard Water Line Passed 6-5-25: mane water line verified under test. Okay to backfill with shading materials.
06/16/2025 COT - HCME - Mechanical Intermediate Passed 6-16-25: mechanical intermediate approved.
06/25/2025 COT - HCBU - Exterior Clips/Sheathing Passed
06/25/2025 COT - HCBU - Framing Passed
06/25/2025 COT - HCBU - Roof Nailing Passed
10/28/2025 COT - HCEL - Electrical Underground Passed Passed 10/28/25 ok to backfill
03/20/2026 BULD - Electrical Clearance Passed Passed 3/20/26 CLEARANCE INCR
04/01/2026 COT - HCME - Mechanical Final Passed
04/01/2026 COT - HCPL - Plumbing Final Passed
04/01/2026 COT - HCEL - Electrical Intermediate Passed 4.1.26
Approved
04/01/2026 COT - HCEL - Grounding/Bonding Passed 4.1.26
passed
04/01/2026 COT - HCEL - Outdoor Lighting Passed
04/09/2026 COT - FCON - Fire - Final Passed
04/20/2026 ENGR Engineering Final Passed
04/21/2026 COT - HCBU - Building Final Passed 4-21-26: building final approved.
04/21/2026 COT - HCEL - Electrical Final Passed 4-21-26: electrical final approved.
04/21/2026 TRSP - ROW - Final/Close-Out Passed all construction for right away connections completed, approved
04/21/2026 COT - HCBU - Building Progress Passed 4-21-26: approved.
05/18/2026 COT - HCBU - CofO Passed All conditions are met and under review. 5/18/2026

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL (SSRS).PDF DOCUMENTS VIEW
LOFC_LETTEROFCOMPLETION (SSRS).PDF DOCUMENTS VIEW
FINAL SI CERT 9-2026-05-11_V1.PDF DOCUMENTS VIEW
BUILDING 9 CALCULATIONS 30X100_V1.PDF DOCUMENTS VIEW
BUILDING 9 DRAWINGS 30X100_V1.PDF DOCUMENTS VIEW
BUILDING 9 - 10 DRAWINGS 30X100_V1.PDF DOCUMENTS VIEW
BUILDING 9-10 CALCULATIONS 30X100_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-SUB1_REV1_PLAN SET_A-FAMILY RITA LOT 09_V1.PDF DOCUMENTS VIEW
CONS-SUB2_PLAN SET_A-FAMILY RITA LOT 9_V2.PDF DOCUMENTS VIEW
SUB2_COMCHECK_A-FAMILY RITA LOT 9_V1.PDF DOCUMENTS VIEW