Permit: TC-COM-1023-02429
Permit Details
Apply Date:
10/17/2023
Applicant:
Cody Mozena
Description:
BLDG 1 - The second phase of a tenant finish for an existing one story single sided dock warehouse / distribution building. DB - ADDITIONAL WORK FOR THIS LOCATION BEING PERFORMED UNDER TC-COM-0323-00817 (3610 E VALENCIA RD TUCSON, AZ 85706)
Permit Reviews
Permit Number - TC-COM-1023-02429
Permit Status: Complete
Permit Description: BLDG 1 - The second phase of a tenant finish for an existing one story single sided dock warehouse / distribution building. DB - ADDITIONAL WORK FOR THIS LOCATION BEING PERFORMED UNDER TC-COM-0323-00817 (3610 E VALENCIA RD TUCSON, AZ 85706)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/15/2023 | COMMERCIAL REVIEW - FULL v.3 | 11/21/2023 | REQUIRES RESUBMIT |
10/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/20/2023 | REQUIRES RESUBMIT |
10/23/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/13/2023 | REQUIRES RESUBMIT |
05/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/08/2024 | APPROVED |
01/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/18/2024 | REQUIRES RESUBMIT |
04/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/30/2024 | APPROVED |
12/20/2023 | COMMERCIAL REVIEW - FULL v.4 | 12/21/2023 | APPROVED |
12/21/2023 | RESTAMP - COMMERCIAL v.1 | 12/23/2023 | APPROVED |
02/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 02/13/2024 | APPROVED |
Conditions
Permit Number - TC-COM-1023-02429
Permit Status: Complete
Permit Description: BLDG 1 - The second phase of a tenant finish for an existing one story single sided dock warehouse / distribution building. DB - ADDITIONAL WORK FOR THIS LOCATION BEING PERFORMED UNDER TC-COM-0323-00817 (3610 E VALENCIA RD TUCSON, AZ 85706)
Date | Description | Comments |
---|---|---|
12/21/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
12/23/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
12/21/2023 | Please submit a separate sign permit for an signs associated with this projet. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1023-02429
Permite Description: BLDG 1 - The second phase of a tenant finish for an existing one story single sided dock warehouse / distribution building. DB - ADDITIONAL WORK FOR THIS LOCATION BEING PERFORMED UNDER TC-COM-0323-00817 (3610 E VALENCIA RD TUCSON, AZ 85706)
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/17/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
04/17/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
04/26/2024 | COT - FCON - Alarm - Final | N/A | Partial Pass | |
04/26/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Fire extinguishers need to be hung in each space. Ok to obtain a TCO level 2 |
05/02/2024 | ENGR Engineering Final | N/A | Partial Pass | TCO2 is approved, once gate and enclosure on east side of building is completed we can approve a full CO |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1023-02429
Permit Description: BLDG 1 - The second phase of a tenant finish for an existing one story single sided dock warehouse / distribution building. DB - ADDITIONAL WORK FOR THIS LOCATION BEING PERFORMED UNDER TC-COM-0323-00817 (3610 E VALENCIA RD TUCSON, AZ 85706)
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/02/2024 | COT - HCBU - Framing | Passed | 3/8/24: framing at clean room per plans ok to proceed. Roof nailing at clean room passed. 3/19/24: framing at ribbon line per plans ok to proceed. Roof nailing at ribbon line passed. 4/2/24: framing at R&D room per plan ok to proceed. roof nailing at R&D room passed. |
|
04/15/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
04/15/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
04/15/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
04/15/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
04/17/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
04/26/2024 | COT - FCON - Sprinkler - Final | Passed | ||
04/29/2024 | COT - HCME - Mechanical Final | Passed | ||
04/29/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
04/30/2024 | COT - FCON - Alarm - Final | Passed | ||
04/30/2024 | COT - FCON - Fire - Final | Passed | ||
04/30/2024 | COT - HCBU - Preslab | Passed | ||
04/30/2024 | COT - HCEL - Electrical Final | Passed | ||
05/21/2024 | ENGR Engineering Final | Passed | ||
05/21/2024 | COT - HCPL - Plumbing Final | Passed | ||
05/22/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
05/23/2024 | COT - HCBU - Building Final | Passed | Ok for TCO level 3 5/23/24: ok for CofO |