Permit Details

Status:
Complete
Type:
Commercial Building
Address:
1302 W AJO WY
Address NEW:
1302 W AJO WY
Apply Date:
10/04/2023
Applicant:
Description:
New solar PV system to supplement resident usage throughout the community. The system will consist of 1471 solar panel mounted on elevated solar racking over the existing parking spaces ("solar carports") and on rooftops in common areas. 1471 modules REV2: 1. We are replacing the existing 100A fuses from the existing main switch gear with new 150A fuses. SEE SHEETS E-601, & E-602. 2. We are replacing the original proposed 110A fuses from the new main solar LI switch (load interrupter 10) with new 150A fuses, and before we have called 3 sets of parallel conductors from the mentioned LI switch up to the POI, but it is actually only 1 set, we fixed that on the SLD. SEE SHEETS E-601, & E-602.

Permit Reviews

Permit Number - TC-COM-1023-02341
Permit Status: Complete
Permit Description: New solar PV system to supplement resident usage throughout the community. The system will consist of 1471 solar panel mounted on elevated solar racking over the existing parking spaces ("solar carports") and on rooftops in common areas. 1471 modules REV2: 1. We are replacing the existing 100A fuses from the existing main switch gear with new 150A fuses. SEE SHEETS E-601, & E-602. 2. We are replacing the original proposed 110A fuses from the new main solar LI switch (load interrupter 10) with new 150A fuses, and before we have called 3 sets of parallel conductors from the mentioned LI switch up to the POI, but it is actually only 1 set, we fixed that on the SLD. SEE SHEETS E-601, & E-602.
Start Date Submittal Complete Date Status  
03/05/2024 RESTAMP - COMMERCIAL v.1 03/14/2024 APPROVED Review Details
01/29/2024 COMMERCIAL REVIEW - FULL v.2 03/05/2024 APPROVED Review Details
05/14/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 05/15/2025 REQUIRES RESUBMIT Review Details
05/19/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 05/20/2025 APPROVED Review Details
10/05/2023 COMMERCIAL REVIEW - FULL v.1 11/08/2023 REQUIRES RESUBMIT Review Details
11/05/2024 RESTAMP - COMMERCIAL v.1 11/07/2024 APPROVED Review Details
10/15/2024 COMMERCIAL REVIEW - FULL v.2 11/05/2024 APPROVED Review Details
08/27/2024 COMMERCIAL REVIEW - FULL v.1 09/27/2024 REQUIRES RESUBMIT Review Details
04/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/29/2025 REQUIRES RESUBMIT Review Details
02/27/2025 COMMERCIAL REVIEW - FULL REVISION v.1 03/11/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-1023-02341
Permit Status: Complete
Permit Description: New solar PV system to supplement resident usage throughout the community. The system will consist of 1471 solar panel mounted on elevated solar racking over the existing parking spaces ("solar carports") and on rooftops in common areas. 1471 modules REV2: 1. We are replacing the existing 100A fuses from the existing main switch gear with new 150A fuses. SEE SHEETS E-601, & E-602. 2. We are replacing the original proposed 110A fuses from the new main solar LI switch (load interrupter 10) with new 150A fuses, and before we have called 3 sets of parallel conductors from the mentioned LI switch up to the POI, but it is actually only 1 set, we fixed that on the SLD. SEE SHEETS E-601, & E-602.
Date Description Comments
05/20/2025 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
11/08/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
11/08/2023 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
11/08/2023 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
11/08/2023 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
11/08/2023 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02341
Permite Description: New solar PV system to supplement resident usage throughout the community. The system will consist of 1471 solar panel mounted on elevated solar racking over the existing parking spaces ("solar carports") and on rooftops in common areas. 1471 modules REV2: 1. We are replacing the existing 100A fuses from the existing main switch gear with new 150A fuses. SEE SHEETS E-601, & E-602. 2. We are replacing the original proposed 110A fuses from the new main solar LI switch (load interrupter 10) with new 150A fuses, and before we have called 3 sets of parallel conductors from the mentioned LI switch up to the POI, but it is actually only 1 set, we fixed that on the SLD. SEE SHEETS E-601, & E-602.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
02/18/2025 COT - CSOL - Electrical Underground Solar Project N/A Partial Pass Partial approval for conduit risers to solar equipment and electrical panels for Systems #1, #2,#3 - okay to backfill progress areas, and okay for concrete placement for equipment pads

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1023-02341
Permit Description: New solar PV system to supplement resident usage throughout the community. The system will consist of 1471 solar panel mounted on elevated solar racking over the existing parking spaces ("solar carports") and on rooftops in common areas. 1471 modules REV2: 1. We are replacing the existing 100A fuses from the existing main switch gear with new 150A fuses. SEE SHEETS E-601, & E-602. 2. We are replacing the original proposed 110A fuses from the new main solar LI switch (load interrupter 10) with new 150A fuses, and before we have called 3 sets of parallel conductors from the mentioned LI switch up to the POI, but it is actually only 1 set, we fixed that on the SLD. SEE SHEETS E-601, & E-602.
Total Completed Inspections - 12
Date Description Inspector Results Comments
01/13/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
01/13/2025 COT - LCBU - Excavation/Rebar/Zoning Passed Approved foundation at each solar canopy column, okay for concrete placement
03/05/2025 COT - CSOL - Electrical Underground Solar Project Passed Approved pull boxes, all underground is complete
04/03/2025 COT - CSOL - Electrical Final Solar Project Passed
04/03/2025 BULD - Electrical Clearance Passed Approved solar structures #1, #2, #3 - DGC Clearance to TEP is required for the solar meter
04/03/2025 ENGR Engineering Final Passed
04/14/2025 COT - LCBU - Building Final Passed
04/14/2025 COT - LCEL - Electrical Final Passed
04/10/2025 TRSP - ROW - Final/Close-Out Passed
04/14/2025 COT - CSOL - Electrical Intermediate Solar Project Passed
04/10/2025 COT - LCBU - Framing Passed
04/14/2025 COT - CSOL - Electrical Progress Solar Project Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
(HW) SPECIAL_INSPECTION_CERTIFICATE-2025-05-16_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-DESERT PUEBLO MOBILE HOME PARK - DRAFTING_5.0 - RESEALED R6 - 24FEB2025 (REVISION 2)_V1.PDF DOCUMENTS VIEW
DESERT PUEBLO, REVISION 2 LETTER, BUILDING DEPARTMENT_V1.PDF DOCUMENTS VIEW
CONS-DESERT PUEBLO MOBILE HOME PARK - DRAFTING_3 - RESEALED R4 10SEP2024 (REVISION 1)_V2.PDF DOCUMENTS VIEW
DESERT PUEBLO, REVISION 1 - CORRECTION 2 LETTER, BUILDING - ZONING DEPARTMENT_V2.PDF DOCUMENTS VIEW
CONS-DESERT PUEBLO MOBILE HOME PARK _E.7 SEALEDCOMBINED_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-DESERT PUEBLO MOBILE HOME PARK _E.7 SEALEDCOMBINED_V2.PDF DOCUMENTS VIEW
DESERT PUEBLO MOBILE HOME PARK, (TAP DRAWING), 11-9-23_V1.PDF DOCUMENTS VIEW