Permit: TC-COM-0924-01821
Permit Details
Apply Date:
09/19/2024
Applicant:
Tanja Weese
Description:
INSTALLATION OF NEW SERVICE ENTRANCE SECTION AND (4) LEVEL 2 EV CAR CHARGERS
Permit Reviews
Permit Number - TC-COM-0924-01821
Permit Status: Complete
Permit Description: INSTALLATION OF NEW SERVICE ENTRANCE SECTION AND (4) LEVEL 2 EV CAR CHARGERS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/19/2024 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 09/23/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0924-01821
Permite Description: INSTALLATION OF NEW SERVICE ENTRANCE SECTION AND (4) LEVEL 2 EV CAR CHARGERS
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2025 | COT - LCEL - Electrical Progress | N/A | Not Applicable | |
| 06/13/2025 | COT - LCEL - Electrical Intermediate | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0924-01821
Permit Description: INSTALLATION OF NEW SERVICE ENTRANCE SECTION AND (4) LEVEL 2 EV CAR CHARGERS
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2025 | COT - LCEL - Electrical Underground | Passed | Passed 6/10/25 ok to backfill | |
| 06/13/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 06/13/2025 | BULD - Electrical Clearance | Passed | Approved new 200A service for EV stations - ECO Clearance to TEP is required | |
| 07/15/2025 | COT - LCEL - Electrical Final | Passed | Approved and complete EV Charging stations |