Permit: TC-COM-0924-01769
Permit Details
Apply Date:
09/12/2024
Applicant:
Eduardo Alvarado
Description:
Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Permit Reviews
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 03/03/2026 | APPROVED |
| 03/28/2025 | COMMERCIAL REVIEW - LIMITED v.3 | 04/17/2025 | APPROVED |
| 01/27/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 02/02/2026 | APPROVED |
| 04/17/2025 | RESTAMP - COMMERCIAL v.1 | 04/21/2025 | APPROVED |
| 12/31/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 01/27/2026 | REQUIRES RESUBMIT |
| 04/27/2026 | SPECIAL INSPECTION REVIEW v.1 | N/A | IN REVIEW |
| 09/16/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 10/01/2024 | REQUIRES RESUBMIT |
| 02/26/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 03/20/2025 | REQUIRES RESUBMIT |
| 10/16/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/10/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/13/2025 | SPECIAL INSPECTION FOR INSPECTION OF FABRICATORS IS REQUIRED. |
Conditions
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
| Date | Description | Comments |
|---|---|---|
| 03/13/2025 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. | |
| 03/13/2025 | SPECIAL INSPECTION FOR CAST-IN-PLACE DEEP FOUNDATION ELEMENTS IS REQUIRED. | |
| 04/21/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/13/2025 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0924-01769
Permite Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2026 | BULD - Electrical Clearance | N/A | Partial Pass | Partial pass for ac side of transformer |
| 02/18/2026 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | Partial pass. Pending tie into equipment. 2/18/2026 |
| 01/27/2026 | COT - LCBU - Framing | N/A | Re-inspection required | 1-27-26: contractor was asked to contact Engineering for a pre slab on a curb & sidewalk. |
| 01/14/2026 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Twelve charging stations on North and East side of charging island. 4” flexible conduit from SES area to East side of charging area. Ok to cover progress areas. |
| 12/18/2025 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | Courtesy inspection. 12/18/2025 |
| 02/18/2026 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Partial pass. Both equipment pads per details A-2 (SES AND CHARGING CABINETS). Bollards in place. Discussion per TEP with a bollard being removed in front of door opening at SES. Okay for concrete placement. 2/18/2026 |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0924-01769
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2026 | BULD - Electrical Clearance | Passed | 4-15-26: okay to energize SES. ECO clearance issued to TEP. | |
| 04/15/2026 | COT - LCEL - Grounding/Bonding | Passed | 4-15-26: grounding/bonding approved. | |
| 04/15/2026 | COT - LCEL - Electrical Underground | Passed | 4-15-26: previously inspected & approved. | |
| 04/15/2026 | COT - LCEL - Electrical Intermediate | Passed | 4-15-26: electrical intermediate approved. | |
| 04/15/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 4-15-26: excavation/reinforcement previously inspected & approved. |