Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0924-01769
Permit Details
Apply Date:
09/12/2024
Applicant:
Eduardo Alvarado
Description:
Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Permit Reviews
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/28/2025 | COMMERCIAL REVIEW - LIMITED v.3 | 04/17/2025 | APPROVED |
| 01/27/2026 | COMMERCIAL REVIEW - FULL REVISION v.2 | 02/02/2026 | APPROVED |
| 04/17/2025 | RESTAMP - COMMERCIAL v.1 | 04/21/2025 | APPROVED |
| 12/31/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 01/27/2026 | REQUIRES RESUBMIT |
| 09/16/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 10/01/2024 | REQUIRES RESUBMIT |
| 02/26/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 03/20/2025 | REQUIRES RESUBMIT |
| 10/16/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/10/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 03/13/2025 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. |
| 03/13/2025 | SPECIAL INSPECTION FOR CAST-IN-PLACE DEEP FOUNDATION ELEMENTS IS REQUIRED. |
| 03/13/2025 | SPECIAL INSPECTION FOR INSPECTION OF FABRICATORS IS REQUIRED. |
| 03/13/2025 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
Conditions
Permit Number - TC-COM-0924-01769
Permit Status: Issued
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
| Date | Description | Comments |
|---|---|---|
| 04/21/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0924-01769
Permite Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2025 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | Courtesy inspection. 12/18/2025 |
| 01/14/2026 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Twelve charging stations on North and East side of charging island. 4” flexible conduit from SES area to East side of charging area. Ok to cover progress areas. |
| 01/27/2026 | COT - LCBU - Framing | N/A | Re-inspection required | 1-27-26: contractor was asked to contact Engineering for a pre slab on a curb & sidewalk. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0924-01769
Permit Description: Tesla is proposing to install their Supercharging station within an existing parking lot. The project includes the installation of (3) charging cabinets, (12) charging posts, (1) switchgear assembly, (1) transformer and (1) meter and (1) wireless access point.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2026 | COT - LCEL - Electrical Underground | Passed | Conduits for SES and equipment cabinets are in place. Two charging stations at West side of site an d one light pole caisson footings added. Ok to,cover progress areas. one inch could it to be added for data monitoring to be added. |